8148 N POTTER AVE 91605

Certificate Information: 8148 N POTTER AVE 91605

Application / Permit
23014-20000-01320
Plan Check / Job No.
B23VN04310
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
21'-0" X 26'-0" One story addition to existing Acessory dwelling unit (ADU per LAMC 12.22 A.33(c) and (d)), Work per WFPP and supplementary engineer detail
Permit Issued
Issued on 7/26/2023
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2023 APPLICANT
Assigned to Plan Check Engineer 4/11/2023 RAMA DABADGE
Corrections Issued 4/12/2023 RAMA DABADGE
Building Plans Picked Up 4/13/2023 APPLICANT
Issued 7/26/2023 APPLICANT
CofO in Progress 12/27/2023 MATTHEW NELSON
Permit Finaled 1/10/2024 RUBEN SALAS
CofO Issued 1/10/2024 RUBEN SALAS
Permit Finaled 1/10/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/18/2023 ROMAN GUTIERREZ
Sewer availability Cleared 4/18/2023 ROMAN GUTIERREZ
Low Impact Development (LID) Cleared 5/4/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/4/2023 NIKKI ZULUETA
Construction near power lines Cleared 7/25/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/31/2023 Partial Approval MATTHEW NELSON
Deputy Drilled-In Anchors 8/17/2023 Conditional Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 8/18/2023 Approved MATTHEW NELSON
PLUMBING-Rough 8/18/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 9/29/2023 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 9/29/2023 Corrections Issued WILLIAM WREN
Green Building Rough 9/29/2023 Approved WILLIAM WREN
HVAC-Rough 9/29/2023 Approved WILLIAM WREN
MERV13>=Rough 9/29/2023 Approved WILLIAM WREN
PLUMBING-Rough 9/29/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/4/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 10/4/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Approved WILLIAM WREN
Insulation 10/12/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 10/12/2023 Approved WILLIAM WREN
Drywall Nailing 10/20/2023 Approved WILLIAM WREN
Shower Pan 10/20/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 10/24/2023 Approved DAVID ANDERSON
Special/Order Compliance 11/3/2023 Approved KIRK SANDERS
Final 12/20/2023 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 12/20/2023 Approved MATTHEW NELSON
Green Building Final 12/20/2023 Corrections Issued MATTHEW NELSON
MERV13>=Final 12/20/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved MATTHEW NELSON
Smoke Detectors 12/20/2023 Approved MATTHEW NELSON
Final 12/27/2023 OK to Issue CofO MATTHEW NELSON
Green Building Final 12/27/2023 Approved MATTHEW NELSON