8148 N POTTER AVE 91605
Certificate Information: 8148 N POTTER AVE 91605
- Application / Permit
- 23014-20000-01320
- Plan Check / Job No.
- B23VN04310
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 21'-0" X 26'-0" One story addition to existing Acessory dwelling unit (ADU per LAMC 12.22 A.33(c) and (d)), Work per WFPP and supplementary engineer detail
- Permit Issued
- Issued on 7/26/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2023 | RAMA DABADGE |
| Corrections Issued | 4/12/2023 | RAMA DABADGE |
| Building Plans Picked Up | 4/13/2023 | APPLICANT |
| Issued | 7/26/2023 | APPLICANT |
| CofO in Progress | 12/27/2023 | MATTHEW NELSON |
| Permit Finaled | 1/10/2024 | RUBEN SALAS |
| CofO Issued | 1/10/2024 | RUBEN SALAS |
| Permit Finaled | 1/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/18/2023 | ROMAN GUTIERREZ |
| Low Impact Development (LID) | Cleared | 5/4/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/4/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 7/25/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/31/2023 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 8/17/2023 | Conditional Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 8/18/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/18/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/29/2023 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 9/29/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 9/29/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 9/29/2023 | Approved | WILLIAM WREN |
| MERV13>=Rough | 9/29/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 9/29/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 10/4/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Approved | WILLIAM WREN |
| Insulation | 10/12/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/12/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 10/20/2023 | Approved | WILLIAM WREN |
| Shower Pan | 10/20/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/24/2023 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 11/3/2023 | Approved | KIRK SANDERS |
| Final | 12/20/2023 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/20/2023 | Approved | MATTHEW NELSON |
| Green Building Final | 12/20/2023 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Final | 12/20/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 12/20/2023 | Approved | MATTHEW NELSON |
| Final | 12/27/2023 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 12/27/2023 | Approved | MATTHEW NELSON |