5552 W EDGEWOOD PL 90019

Certificate Information: 5552 W EDGEWOOD PL 90019

Application / Permit
23014-20000-01315
Plan Check / Job No.
B23VN04299
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
28'-7" X 7'-0" ADDITION TO ENLARGE EXISTING BEDROOM AND ADD NEW CLOSET AND BATHROOM - PER ENGINEER
Permit Issued
Issued on 6/21/2023
Issuing Office
Current Status
CofO Issued on 12/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2023 APPLICANT
Assigned to Plan Check Engineer 4/11/2023 JEROME MAGAT PALMA
Corrections Issued 4/12/2023 JEROME MAGAT PALMA
Building Plans Picked Up 4/18/2023 APPLICANT
Plan Check Approved 6/16/2023 DANIEL ABRAMYAN
Issued 6/21/2023 APPLICANT
CofO in Progress 12/13/2023 RICHARD DOCKUS
Permit Finaled 12/30/2023 DEROLD HAUFF
CofO Issued 12/30/2023 DEROLD HAUFF
Permit Finaled 12/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/12/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/13/2023 JEANIE LAM
HPOZ Cleared 6/14/2023 AMANDA KAINER

Contact Information

Contractor Creative Home Remodeling Group Inc; Lic. No.: 943341-B 11333 MOORPARK ST #214      STUDIO CITY, CA 91602

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/8/2023 Corrections Issued BRENDAN MORELLI
METHANE-Barrier 8/8/2023 Approved BRENDAN MORELLI
METHANE-Subgrade 8/8/2023 Approved BRENDAN MORELLI
Footing/Foundation/Slab 8/10/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Approved ROY SPAULDING
PLUMBING-Rough 8/23/2023 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Approved ROY SPAULDING
ELECTRICAL-Rough 9/14/2023 Approved RICHARD DOCKUS
PLUMBING-Rough 9/14/2023 Approved RICHARD DOCKUS
Wood Frame 9/14/2023 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 9/22/2023 Approved RICHARD DOCKUS
Green Building Rough 9/22/2023 Approved RICHARD DOCKUS
METHANE-Rough 9/22/2023 Approved RICHARD DOCKUS
Insulation 9/28/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 9/28/2023 Partial Approval RICHARD DOCKUS
Drywall Nailing 10/4/2023 Approved RICHARD DOCKUS
Shower Pan 10/4/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 10/24/2023 Approved RICHARD DOCKUS
Final 11/30/2023 Corrections Issued RICHARD DOCKUS
Green Building Final 11/30/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/30/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 11/30/2023 Approved RICHARD DOCKUS
Final 12/12/2023 OK to Issue CofO RICHARD DOCKUS