3694 N VALLEY MEADOW ROAD 91403

Certificate Information: 3694 N VALLEY MEADOW ROAD 91403

Application / Permit
23014-20000-01313
Plan Check / Job No.
B23VN04296
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
6'-4" X 23'-10" & 2'-6" X 10'-4" ADDITION AND REMODEL AND ENCLOSURE OF 4'-10" X 4'-6" & 6'-0" X 10'-4" PORTION UNDER EXISTING ROOF FOR EXISTING SINGLE FAMILY DWELLING - PER ENGINEER
Permit Issued
Issued on 3/12/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2023 APPLICANT
Assigned to Plan Check Engineer 4/10/2023 ARTIN ZARUKIAN
Corrections Issued 4/11/2023 ARTIN ZARUKIAN
Building Plans Picked Up 4/12/2023 APPLICANT
Applicant returned to address corrections 5/18/2023 DANIEL ABRAMYAN
Plan Check Approved 6/7/2023 DANIEL ABRAMYAN
Issued 3/12/2024 APPLICANT
CofO in Progress 5/14/2025 THOMAS FINNILA
Permit Finaled 10/1/2025 MICHAEL PELHAM
CofO Issued 10/1/2025 MICHAEL PELHAM
Permit Finaled 10/1/2025 MICHAEL PELHAM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/17/2023 NIKKI ZULUETA
Sewer availability Cleared 4/17/2023 NIKKI ZULUETA
Grading Pre-Inspection Cleared 4/26/2023 ALEXANDER HELFER
Eng Process Fee Ord 176,300 Cleared 6/5/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 3/12/2024 TAL SHEMEN
BHO/Hillside ordinance Cleared 3/12/2024 TAL SHEMEN
BHO/Hillside ordinance Cleared 3/12/2024 TAL SHEMEN
BHO/Hillside ordinance Cleared 3/12/2024 TAL SHEMEN
BHO/Hillside ordinance Cleared 3/12/2024 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/22/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/22/2024 Approved VINCENT HANLEY
ELECTRICAL-Rough 6/20/2024 Partial Inspection THOMAS FINNILA
BUILDING-Rough-Frame 9/26/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 9/26/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Corrections Issued THOMAS FINNILA
HVAC-Rough 9/26/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/4/2024 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 10/16/2024 Partial Approval JOHN KIDWELL
Green Building Rough 10/16/2024 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 4/11/2025 Approved THOMAS FINNILA
Drywall Nailing 4/11/2025 Approved THOMAS FINNILA
Green Building Rough 4/11/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 4/22/2025 Approved THOMAS FINNILA
Final 4/22/2025 Corrections Issued THOMAS FINNILA
Final 4/28/2025 Not Ready for Inspection MORRIS JACKSON
Green Building Final 4/28/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 4/28/2025 Not Ready for Inspection MORRIS JACKSON
HVAC-Final 5/12/2025 Conditional Approval THOMAS FINNILA
PLUMBING-Final 5/12/2025 Approved THOMAS FINNILA
Final 5/13/2025 OK to Issue CofO THOMAS FINNILA
Smoke Detectors 5/13/2025 Approved THOMAS FINNILA