1759 S ALVIRA ST 90035

Certificate Information: 1759 S ALVIRA ST 90035

Application / Permit
23014-20000-01301
Plan Check / Job No.
B23VN04246
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRR. SHAPED ADDITION TO THE FRONT & REAR OF (E) ONE-STORY SINGLE FAMILY DWELLING AND NEW 36'-3" x 38' IRR. SHAPED 2ND FLOOR ADDITION, NEW OPEN TRELLIS @ FRONT & SIDE AND REMODEL; NFPA-13D THRU-OUT
Permit Issued
Issued on 8/24/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 SEAN SHAHMIRI
Corrections Issued 4/24/2023 SEAN SHAHMIRI
Quality Review Completed 4/25/2023 OMID HEDAYAT
Building Plans Picked Up 4/28/2023 APPLICANT
Applicant returned to address corrections 6/29/2023 SEAN SHAHMIRI
Plan Check Approved 6/29/2023 SEAN SHAHMIRI
Issued 8/24/2023 APPLICANT
CofO in Progress 8/27/2024 ARTHUR NEGRETE
Permit Finaled 11/11/2024 DEROLD HAUFF
CofO Issued 11/11/2024 DEROLD HAUFF
Permit Finaled 11/11/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/17/2023 MSTAFA AL-MSARI
Eng Process Fee Ord 176,300 Cleared 6/23/2023 MSTAFA AL-MSARI
Sewer availability Cleared 6/23/2023 MSTAFA AL-MSARI
Low Impact Development (LID) Cleared 8/9/2023 SAMUEL LINN

Contact Information

Contractor A R M Builders Inc; Lic. No.: 915352-B 1080 S LA CIENEGA #311      LOS ANGELES, CA 90035
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/10/2023 Conditional Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/17/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Partial Approval JOSE AVILA
METHANE-Barrier 10/30/2023 Approved JOSE AVILA
METHANE-Subgrade 10/30/2023 Approved JOSE AVILA
Deputy Drilled-In Anchors 10/31/2023 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/9/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Approved RONNIE MINDANAO
HVAC-Rough 12/22/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 1/3/2024 Approved RONNIE MINDANAO
HVAC-Rough 1/3/2024 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 1/3/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 1/5/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 1/5/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 1/8/2024 Conditional Approval RONNIE MINDANAO
Green Building Rough 1/8/2024 Not Ready for Inspection RONNIE MINDANAO
Deputy Wood Construction 1/9/2024 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/10/2024 Corrections Issued STUART CHAPMAN
Insulation 1/17/2024 Partial Approval STUART CHAPMAN
Shower Pan 1/17/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 1/24/2024 Partial Approval STUART CHAPMAN
Drywall Nailing 1/25/2024 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 1/25/2024 Approved STUART CHAPMAN
Green Building Rough 1/26/2024 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 1/26/2024 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 1/30/2024 Approved JOSE MACIAS
ELECTRICAL-Final 6/18/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 7/3/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 7/9/2024 Corrections Issued ALIZAH MAYAGOITIA
Drywall Nailing 7/9/2024 Partial Inspection ALIZAH MAYAGOITIA
Final 7/9/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 7/9/2024 Approved ALIZAH MAYAGOITIA
Green Building Final 7/9/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 7/9/2024 Approved ALIZAH MAYAGOITIA
HVAC-Final 7/9/2024 Approved ALIZAH MAYAGOITIA
METHANE-Final 7/9/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 7/9/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/9/2024 Approved ARTHUR NEGRETE
Drywall Nailing 8/9/2024 Approved ARTHUR NEGRETE
Final 8/9/2024 Partial Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 8/9/2024 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 8/9/2024 Approved ARTHUR NEGRETE
Special/Order Compliance 8/9/2024 Not Ready for Inspection AMIR NAZARIAN
Final 8/26/2024 OK to Issue CofO ARTHUR NEGRETE