14836-14838 W LANARK ST 91402
Certificate Information: 14836-14838 W LANARK ST 91402
- Application / Permit
- 23014-20000-01297
- Plan Check / Job No.
- B23VN04224
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-4" X 18'-0 REC.ROOM AND 7'-0" X 18'-0" ATTACHED CARPORT TO (N) ATTACHED ACCESSORY DWELLING UNIT (466 S.F ) PER LAMC 12.22 A.33(c) AND (e). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 4/10/2023 | APPLICANT |
Assigned to Plan Check Engineer | 4/14/2023 | MIROOSH KHACHATOORIAN |
Corrections Issued | 4/15/2023 | MIROOSH KHACHATOORIAN |
Applicant returned to address corrections | 4/25/2023 | MIROOSH KHACHATOORIAN |
Applicant returned to address corrections | 5/2/2023 | SUNMIN LEE |
Plan Check Approved | 5/4/2023 | MIROOSH KHACHATOORIAN |
Issued | 5/9/2023 | APPLICANT |
CofO in Progress | 9/21/2023 | GREGG CUMMINGS |
Permit Finaled | 11/18/2023 | RUBEN SALAS |
CofO Issued | 11/18/2023 | RUBEN SALAS |
Permit Finaled | 11/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
Address approval | Cleared | 4/18/2023 | ROMAN GUTIERREZ |
Roof/Waste drainage to street | Cleared | 4/18/2023 | ROMAN GUTIERREZ |
Sewer availability | Cleared | 4/18/2023 | ROMAN GUTIERREZ |
Eng Process Fee Ord 176,300 | Cleared | 4/21/2023 | ROMAN GUTIERREZ |
Contact Information
Contractor | ; Lic. No.: 851344-B | , |
Engineer | Kaballo,, Amir; Lic. No.: C90707 | 152 S SWALL DR BEVERLY HILLS, CA 90211 |
Inspector Information
VINCENT HANLEY, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Underground Mechanical | 6/21/2023 | Corrections Issued | MATTHEW NELSON |
Footing/Foundation/Slab | 6/22/2023 | Partial Approval | MATTHEW NELSON |
Footing/Foundation/Slab | 6/28/2023 | Corrections Issued | GREGG CUMMINGS |
Footing/Foundation/Slab | 6/28/2023 | Off-Hour Fees Due | |
PLUMBING-Rough | 6/28/2023 | Partial Approval | GREGG CUMMINGS |
Excavation/Setback/Form/Re-Bar | 6/29/2023 | Approved | GREGG CUMMINGS |
Footing/Foundation/Slab | 6/29/2023 | Approved | GREGG CUMMINGS |
Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Partial Approval | DAVID MATSON |
PLUMBING-Rough | 7/19/2023 | Not Ready for Inspection | DAVID MATSON |
ELECTRICAL-Rough | 7/26/2023 | Corrections Issued | GREGG CUMMINGS |
HVAC-Rough | 7/26/2023 | Corrections Issued | GREGG CUMMINGS |
Interior/Exterior Lathing | 7/26/2023 | Partial Approval | GREGG CUMMINGS |
PLUMBING-Rough | 7/26/2023 | Approved | GREGG CUMMINGS |
Shower Pan | 7/26/2023 | Approved | GREGG CUMMINGS |
BUILDING-Rough-Frame | 8/7/2023 | Approved | GREGG CUMMINGS |
ELECTRICAL-Rough | 8/7/2023 | Approved | GREGG CUMMINGS |
HVAC-Rough | 8/7/2023 | Approved | GREGG CUMMINGS |
Insulation | 8/7/2023 | Partial Approval | GREGG CUMMINGS |
Interior/Exterior Lathing | 8/7/2023 | Partial Approval | GREGG CUMMINGS |
Insulation | 8/11/2023 | Approved | GREGG CUMMINGS |
Drywall Nailing | 8/15/2023 | Approved | GREGG CUMMINGS |
Final | 9/11/2023 | Corrections Issued | GREGG CUMMINGS |
HVAC-Final | 9/11/2023 | Approved | GREGG CUMMINGS |
SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Approved | GREGG CUMMINGS |
Smoke Detectors | 9/11/2023 | Approved | GREGG CUMMINGS |
Final | 9/18/2023 | Not Ready for Inspection | GREGG CUMMINGS |
ELECTRICAL-Final | 9/21/2023 | Approved | GREGG CUMMINGS |
Final | 9/21/2023 | OK to Issue CofO | GREGG CUMMINGS |
PLUMBING-Final | 9/21/2023 | Approved | GREGG CUMMINGS |