8475 N RINCON AVE 91352

Certificate Information: 8475 N RINCON AVE 91352

Application / Permit
23014-20000-01279
Plan Check / Job No.
B23VN04181
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Irregular shaped 23'-10" x 20' bedroom and bathroom addition to (e) sfd
Permit Issued
Issued on 4/13/2023
Issuing Office
Valley
Current Status
Issued on 4/13/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2023 APPLICANT
Assigned to Plan Check Engineer 4/3/2023 ANGELICA DAVE
Corrections Issued 4/3/2023 ANGELICA DAVE
Plan Check Approved 4/13/2023 ALEC MOUSAKHANIAN
Issued 4/13/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/10/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 4/10/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/11/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/31/2023 Conditional Approval RUBEN SALAS
Footing/Foundation/Slab 8/7/2023 Approved MATTHEW NELSON
PLUMBING-Rough 8/16/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/17/2023 Partial Approval MATTHEW NELSON
Green Building Rough 8/17/2023 Not Ready for Inspection MATTHEW NELSON
Insulation 9/5/2023 Partial Approval RYAN SALAZAR
Wood Frame 9/5/2023 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 10/5/2023 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 10/5/2023 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/16/2023 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 10/16/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/19/2023 Approved DAVID ANDERSON
PLUMBING-Rough 10/19/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 10/26/2023 Not Ready for Inspection DAVID ANDERSON
Green Building Rough 10/26/2023 Not Ready for Inspection DAVID ANDERSON
Interior/Exterior Lathing 11/7/2023 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 12/11/2023 Corrections Issued MATTHEW NELSON
Insulation 12/11/2023 Conditional Approval MATTHEW NELSON
BUILDING-Rough-Frame 12/12/2023 Approved MATTHEW NELSON
Green Building Rough 12/12/2023 Approved MATTHEW NELSON
Drywall Nailing 12/19/2023 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 12/19/2023 Approved MISAEL ESPARZA