8418 N DENSMORE AVE 91343

Certificate Information: 8418 N DENSMORE AVE 91343

Application / Permit
23014-20000-01275
Plan Check / Job No.
B23VN04172
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING (18'-0"x20'-0"), 348 SQFT DETACHED 2-CAR GARAGE INTO AN ADU W/(14'-5"x10'-6"), 151 SQFT ADDITION USING WFPP PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 8/9/2023
Issuing Office
Valley
Current Status
Issued on 8/9/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 PETER MOSESIAN
Corrections Issued 4/23/2023 PETER MOSESIAN
Quality Review Completed 4/27/2023 OMID HEDAYAT
Building Plans Picked Up 5/3/2023 APPLICANT
Plan Check Approved 8/9/2023 PETER MOSESIAN
Issued 8/9/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/12/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 5/12/2023 NIKKI ZULUETA
Sewer availability Cleared 5/25/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 5/31/2023 NIKKI ZULUETA
Construction near power lines Cleared 8/2/2023 RIDWAN HARDY

Contact Information

Contractor Pavlovich Construction Co; Lic. No.: 388868-B 22817 VENTURA BLVD 1001      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/30/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 8/30/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 10/2/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 10/2/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 10/2/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 10/2/2023 Corrections Issued RAUL OLAGI
Sewer 10/2/2023 Approved RAUL OLAGI
Underground Mechanical 10/2/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 2/29/2024 Approved RAUL OLAGI
PLUMBING-Rough 2/29/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/14/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 3/14/2024 Partial Approval RAUL OLAGI
Green Building Rough 3/14/2024 Approved RAUL OLAGI
HVAC-Rough 3/14/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 3/14/2024 Partial Approval RAUL OLAGI
Shower Pan 3/14/2024 Approved RAUL OLAGI
Insulation 3/26/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 4/2/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/24/2024 Approved RAUL OLAGI
Underground Mechanical 4/24/2024 Approved RAUL OLAGI
Final 12/16/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 12/16/2024 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 12/16/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Final 12/27/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 12/27/2024 Corrections Issued JOSE AVILA
Final 3/21/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 3/21/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 3/21/2025 Approved GAREN HAYRAPETYAN