5502 N KLUMP AVE 1-93 91601
Certificate Information: 5502 N KLUMP AVE 1-93 91601
- Application / Permit
- 23014-20000-01259
- Plan Check / Job No.
- B23VN04132
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-Plan: CONVERT 13 (E) PARKING SPACE (7 STD.+6 COMP.) TO (9) ADU AT BASEMENT. See Cooment.
- Permit Issued
- Issued on 4/30/2024
- Issuing Office
- Current Status
- Issued on 4/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | TSE MING HUANG |
| Corrections Issued | 4/28/2023 | TSE MING HUANG |
| Quality Review Completed | 5/2/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 5/19/2023 | TSE MING HUANG |
| Plan Check Approved | 4/29/2024 | TSE MING HUANG |
| Issued | 4/30/2024 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/10/2023 | JAZMIN ROQUE |
| Green Code | Cleared | 5/16/2023 | AARON COSTA |
| Address approval | Cleared | 5/26/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/26/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2023 | ROMAN GUTIERREZ |
| DAS Clearance | Cleared | 6/30/2023 | NORLITO MEDRANO |
| Fire Marshal Fire Life Safety | Cleared | 1/4/2024 | PEJMAN NOORI |
| Tenant Habitability Plan | Cleared | 4/4/2024 | RICARDO BOHORQUEZ |
Contact Information
| Architect | Albert,, Stephen M; Lic. No.: C9412 | 2032 STONER AVE LOS ANGELES, CA 90025 |
| Contractor | Owner-Builder | , |
| Engineer | Soliman,, John; Lic. No.: C80833 | 13785 PELICAN DR RANCHO CUCAMONGA, CA 91739 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Masonry Wall/Backfill | 7/27/2026 |
Inspection Request History
| Footing/Foundation/Slab | 6/4/2026 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 6/5/2026 | Conditional Approval | JEFFREY DURAN |
| Reinforced Concrete Frame | 6/5/2026 | Corrections Issued | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 6/11/2026 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 6/18/2026 | Partial Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 7/6/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Masonry Wall/Backfill | 7/8/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Footing/Foundation/Slab | 7/13/2026 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 7/20/2026 | Not Ready for Inspection | ROBERT DAVIS |