5320 N VELOZ AVE 91356

Certificate Information: 5320 N VELOZ AVE 91356

Application / Permit
23014-20000-01248
Plan Check / Job No.
B23VN04077
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
31'-4" X 32' IRREG SHAPED ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/15/2023
Issuing Office
Current Status
CofO Issued on 4/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2023 APPLICANT
Assigned to Plan Check Engineer 4/5/2023 JEROME MAGAT PALMA
Corrections Issued 4/6/2023 JEROME MAGAT PALMA
Building Plans Picked Up 4/7/2023 APPLICANT
Plan Check Approved 6/15/2023 JEROME MAGAT PALMA
Issued 6/15/2023 APPLICANT
CofO in Progress 4/15/2024 JOHN KIDWELL
Permit Finaled 4/18/2024 DANIEL ORRANTE
CofO Issued 4/18/2024 DANIEL ORRANTE
Permit Finaled 4/18/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/12/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/24/2023 LEE GUILBEAUX
Sewer availability Cleared 4/24/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 5/17/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 5/18/2023 LEE GUILBEAUX
Construction near power lines Cleared 6/1/2023 WALTER RAMIREZ
GPI Written Notices Cleared 6/15/2023 JEROME MAGAT PALMA
Grading Pre-Inspection Cleared 6/15/2023 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/26/2023 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 8/3/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 8/3/2023 Approved SEAN HAUPT
Underground Mechanical 8/23/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 10/16/2023 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 10/16/2023 Approved SEAN HAUPT
HVAC-Rough 10/16/2023 Approved SEAN HAUPT
PLUMBING-Rough 10/16/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 10/30/2023 Approved SEAN HAUPT
Shower Pan 10/30/2023 Approved SEAN HAUPT
Drywall Nailing 11/30/2023 Approved SEAN HAUPT
Insulation 11/30/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 1/19/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/20/2024 Approved JOHN KIDWELL
ELECTRICAL-Final 3/20/2024 Approved JOHN KIDWELL
Final 3/20/2024 Corrections Issued JOHN KIDWELL
Green Building Final 3/20/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 3/20/2024 Approved JOHN KIDWELL
HVAC-Final 3/20/2024 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 3/20/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 3/20/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Approved JOHN KIDWELL
Service/Power Release 3/29/2024 Approved JOHN KIDWELL
Final 4/12/2024 OK to Issue CofO JOHN KIDWELL
Green Building Final 4/12/2024 Approved JOHN KIDWELL