5320 N VELOZ AVE 91356
Certificate Information: 5320 N VELOZ AVE 91356
- Application / Permit
- 23014-20000-01248
- Plan Check / Job No.
- B23VN04077
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 31'-4" X 32' IRREG SHAPED ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/15/2023
- Issuing Office
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 4/6/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/7/2023 | APPLICANT |
| Plan Check Approved | 6/15/2023 | JEROME MAGAT PALMA |
| Issued | 6/15/2023 | APPLICANT |
| CofO in Progress | 4/15/2024 | JOHN KIDWELL |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
| CofO Issued | 4/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/24/2023 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 5/17/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 5/18/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 6/1/2023 | WALTER RAMIREZ |
| GPI Written Notices | Cleared | 6/15/2023 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 6/15/2023 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/26/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 8/3/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 8/3/2023 | Approved | SEAN HAUPT |
| Underground Mechanical | 8/23/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/16/2023 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 10/16/2023 | Approved | SEAN HAUPT |
| HVAC-Rough | 10/16/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 10/16/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 10/30/2023 | Approved | SEAN HAUPT |
| Shower Pan | 10/30/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 11/30/2023 | Approved | SEAN HAUPT |
| Insulation | 11/30/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/19/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 3/20/2024 | Approved | JOHN KIDWELL |
| Final | 3/20/2024 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 3/20/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 3/20/2024 | Approved | JOHN KIDWELL |
| HVAC-Final | 3/20/2024 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 3/20/2024 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 3/20/2024 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 3/29/2024 | Approved | JOHN KIDWELL |
| Final | 4/12/2024 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 4/12/2024 | Approved | JOHN KIDWELL |