14747 W COBALT ST 91342

Certificate Information: 14747 W COBALT ST 91342

Application / Permit
23014-20000-01247
Plan Check / Job No.
B23VN04042
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan 1st story 44 sf addition and 2nd STORY 1006 sf ADDITION AND REMODEL EXISTING HOUSE and proposed 300 sf covered patio. **** SFD TO BE FIRE SPRINKLERED NFPA-13D****
Permit Issued
Issued on 12/17/2023
Issuing Office
Current Status
Issued on 12/17/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/31/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 CRYSTEL MAALOUF
Corrections Issued 4/26/2023 CRYSTEL MAALOUF
Quality Review Completed 5/18/2023 FARUK SEZER
Plan Check Approved 9/5/2023 CRYSTEL MAALOUF
Issued 12/17/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/20/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/13/2023 CARLOS AGUILERA
Sewer availability Cleared 6/13/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 9/24/2024 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 11/21/2024 Partial Approval KEVIN BERBERYAN
Deputy Steel/Welding 11/21/2024 Conditional Approval KEVIN BERBERYAN
MERV13>=Rough 11/21/2024 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 1/7/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 1/7/2025 Approved KEVIN BERBERYAN
Deputy Steel/Welding 1/17/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 4/9/2025 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 4/9/2025 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 4/9/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 4/9/2025 Partial Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 4/21/2025 Approved KEVIN BERBERYAN
HVAC-Rough 4/21/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 4/21/2025 Approved KEVIN BERBERYAN
Insulation 4/24/2025 Corrections Issued KEVIN BERBERYAN
Insulation 4/28/2025 Approved KEVIN BERBERYAN
Drywall Nailing 5/2/2025 Approved KEVIN BERBERYAN