7013-7013 1/2 W GREELEY ST 91042
Certificate Information: 7013-7013 1/2 W GREELEY ST 91042
- Application / Permit
- 23014-20000-01245
- Plan Check / Job No.
- B23VN04040
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW TWO STORY 2 UNIT ADU OVER TUCK IN PARKING/GARAGE
- Permit Issued
- Issued on 7/20/2023
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | JAD BASMA |
| Corrections Issued | 4/22/2023 | JAD BASMA |
| Quality Review Completed | 5/1/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 5/17/2023 | JAD BASMA |
| Applicant returned to address corrections | 6/23/2023 | JAD BASMA |
| Applicant returned to address corrections | 7/7/2023 | JAD BASMA |
| Plan Check Approved | 7/20/2023 | JAD BASMA |
| Issued | 7/20/2023 | APPLICANT |
| CofO in Progress | 2/18/2026 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
| CofO Issued | 3/12/2026 | RUBEN SALAS |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2023 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 4/24/2023 | ASHLEY RODARTE |
| Sewer availability | Cleared | 4/24/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 5/10/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/12/2023 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 6/14/2023 | VASIL MIHALEV |
| Specific Plan | Cleared | 6/16/2023 | SARAH HOUNSELL |
| Grading Pre-Inspection | Cleared | 7/19/2023 | JAD BASMA |
Contact Information
| Contractor | Frame J Properties; Lic. No.: 625622-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/22/2023 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 8/30/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Corrections Issued | WILLIAM WREN |
| Deputy Wood Construction | 9/14/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/15/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 11/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 11/15/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/15/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 4/15/2024 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/26/2024 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 6/26/2024 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Partial Approval | WILLIAM WREN |
| HVAC-Rough | 7/10/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 7/10/2024 | Approved | WILLIAM WREN |
| Deputy Wood Construction | 7/12/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 7/15/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 7/15/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 7/15/2024 | Approved | WILLIAM WREN |
| Insulation | 7/23/2024 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/23/2024 | Partial Approval | GREGG CUMMINGS |
| Insulation | 7/31/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 8/14/2024 | Approved | WILLIAM WREN |
| Underground Mechanical | 9/16/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 9/19/2024 | Partial Approval | WILLIAM WREN |
| Underground Mechanical | 10/1/2024 | Partial Approval | WILLIAM WREN |
| Underground Mechanical | 10/23/2024 | Approved | WILLIAM WREN |
| Sewer | 2/4/2025 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 3/4/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Sewer | 3/18/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Final | 11/14/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Final | 11/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 11/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Service/Power Release | 11/14/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 12/17/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 1/20/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 1/20/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Not Required | NICHOLAS TROWBRIDGE |
| Service/Power Release | 1/20/2026 | Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 1/20/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 2/17/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |