5849 N VESPER AVE 91411
Certificate Information: 5849 N VESPER AVE 91411
- Application / Permit
- 23014-20000-01239
- Plan Check / Job No.
- B23VN04022
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ATTACHED GARAGE, LAUNDRY ROOM, AND STORAGE ROOM. AND ADD NEW ADDITION AND MAJOR REMODEL TO SINGLE FAMILY DWELLING. (NFPA 13D FIRE SPRINKLERS REQUIRED)
- Permit Issued
- Issued on 2/26/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 4/6/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/12/2023 | APPLICANT |
| Applicant returned to address corrections | 9/8/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 12/29/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 2/26/2024 | MOHAMMAD ESMAILI |
| Issued | 2/26/2024 | APPLICANT |
| CofO in Progress | 2/5/2025 | RYAN SALAZAR |
| Permit Finaled | 2/7/2025 | RUBEN SALAS |
| CofO Issued | 2/7/2025 | RUBEN SALAS |
| Permit Finaled | 2/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/14/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/29/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 2/21/2024 | ROGELIO CORTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/2/2024 | Conditional Approval | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 4/2/2024 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/3/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 4/23/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/21/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/21/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/22/2024 | Corrections Issued | RYAN SALAZAR |
| Deputy Wood Construction | 5/22/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/22/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 5/22/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/7/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/7/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 6/7/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/12/2024 | Approved | RYAN SALAZAR |
| Insulation | 6/12/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/5/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 7/5/2024 | Approved | RYAN SALAZAR |
| Final | 12/20/2024 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 12/20/2024 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 12/20/2024 | Approved | RYAN SALAZAR |
| Final | 2/6/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 2/6/2025 | Approved | RYAN SALAZAR |