18538 W NAPA ST 91324
Certificate Information: 18538 W NAPA ST 91324
- Application / Permit
- 23014-20000-01233
- Plan Check / Job No.
- B23VN04004
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE IRREGULAR SHAPE 24'6" X 24' WITH ATTACHED GRANNY FLAT IRREGULAR SHAPE 15'-6" X 24' AND NEW ADDITION 13' X 20'3" PER LAMC 12.22 A.33(c) and (d). WORK DONE PER WFPP "COMPLY WITH DEPARTMENT ORDER effective date 03/01/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2023 | SERGIO MUNIZ |
| Corrections Issued | 4/5/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 4/11/2023 | APPLICANT |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 4/17/2025 | MARK DOVICO |
| Permit Finaled | 6/2/2025 | DAVID JAMES |
| CofO Issued | 6/2/2025 | DAVID JAMES |
| Permit Finaled | 6/2/2025 | DAVID JAMES |
Permit Application Clearance Information
| ZA Case | Cleared | 5/9/2023 | ASHLEY RODARTE |
| Address approval | Cleared | 5/12/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 5/12/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 5/16/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 7/25/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2023 | Approved | MARK DOVICO |
| Pre-Inspection | 10/6/2023 | Corrections Issued | MARK DOVICO |
| BUILDING-Rough-Frame | 11/27/2023 | Corrections Issued | MARK DOVICO |
| Final | 11/27/2023 | Corrections Issued | MARK DOVICO |
| Footing/Foundation/Slab | 11/27/2023 | Corrections Issued | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 11/27/2023 | SGSOV Not Ready | MARK DOVICO |
| Smoke Detectors | 11/27/2023 | Approved | MARK DOVICO |
| ELECTRICAL-Rough | 1/2/2024 | Approved | MARK DOVICO |
| PLUMBING-Rough | 1/2/2024 | Approved | MARK DOVICO |
| Pre-Inspection | 1/2/2024 | Approved | MARK DOVICO |
| Insulation | 1/8/2024 | Corrections Issued | MARK DOVICO |
| Pre-Inspection | 1/8/2024 | Approved | MARK DOVICO |
| BUILDING-Rough-Frame | 1/23/2024 | Approved | MARK DOVICO |
| HVAC-Rough | 1/23/2024 | Approved | MARK DOVICO |
| Insulation | 1/23/2024 | Approved | MARK DOVICO |
| Pre-Inspection | 1/23/2024 | Approved | MARK DOVICO |
| Final | 1/30/2024 | Corrections Issued | MARK DOVICO |
| Footing/Foundation/Slab | 1/30/2024 | Approved | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 1/30/2024 | SGSOV Not Ready | MARK DOVICO |
| Final | 2/1/2024 | Conditional Approval | MARK DOVICO |
| Pre-Inspection | 2/1/2024 | Approved | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Approved | MARK DOVICO |
| Final | 4/17/2025 | OK to Issue CofO | MARK DOVICO |