447 1/2-3/4 E 74TH ST 90003
Certificate Information: 447 1/2-3/4 E 74TH ST 90003
- Application / Permit
- 23014-20000-01213
- Plan Check / Job No.
- B23VN03940
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 6' x 25'ADDITION TO & CONVERT ATTACHED 560 SF GARAGE INTO (N) 710 SF ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e), ALL WORK PER ENG.
- Permit Issued
- Issued on 5/19/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2023 | RAMA DABADGE |
| Corrections Issued | 4/10/2023 | RAMA DABADGE |
| Building Plans Picked Up | 4/13/2023 | APPLICANT |
| Applicant returned to address corrections | 5/8/2023 | LUISANGEL VALENZUELA |
| Issued | 5/19/2023 | APPLICANT |
| CofO in Progress | 3/8/2024 | MICHAEL LEWIS |
| CofO Issued | 3/18/2024 | DEROLD HAUFF |
| Permit Finaled | 3/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 4/20/2023 | HELEN JADALI |
| ZI | Cleared | 4/20/2023 | HELEN JADALI |
| Tenant Habitability Plan | Cleared | 5/1/2023 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 5/4/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2023 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 5/4/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 5/4/2023 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/24/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/24/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 7/24/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Approved | MICHAEL LEWIS |
| Insulation | 9/28/2023 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 9/28/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/4/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 10/4/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/4/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/13/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 10/13/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 10/13/2023 | Approved | MICHAEL LEWIS |
| Insulation | 11/7/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 11/7/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 11/17/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 1/12/2024 | No Access for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 2/7/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 2/7/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 2/7/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 2/7/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 2/7/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Not Required | MICHAEL LEWIS |
| Smoke Detectors | 2/7/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 3/1/2024 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 3/1/2024 | Approved | MICHAEL LEWIS |
| Service/Power Release | 3/1/2024 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 3/1/2024 | Approved | MICHAEL LEWIS |
| Final | 3/8/2024 | OK to Issue CofO | MICHAEL LEWIS |