10803 W CANTLAY ST 91352
Certificate Information: 10803 W CANTLAY ST 91352
- Application / Permit
- 23014-20000-01210
- Plan Check / Job No.
- B23VN03931
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 6' X 29'4" ADDITION TO (E) SINGLE FAMILY DWELLING TO EXPAND EXISTING KITCHEN AND DINING ROOM. WORK TO BE DONE PER ENGINEER.
- Permit Issued
- Issued on 4/25/2023
- Issuing Office
- Valley
- Current Status
- Issued on 4/25/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2023 | RAMA DABADGE |
| Corrections Issued | 4/6/2023 | RAMA DABADGE |
| Building Plans Picked Up | 4/13/2023 | APPLICANT |
| Issued | 4/25/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/20/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/17/2023 | Approved | JOHN HAYES |
| Deputy Drilled-In Anchors | 8/24/2023 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 8/25/2023 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 9/7/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 9/7/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 9/7/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 9/7/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 10/3/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/3/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/19/2023 | Approved | JOHN HAYES |
| Green Building Rough | 10/19/2023 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 10/19/2023 | Approved | JOHN HAYES |
| Insulation | 10/31/2023 | Conditional Approval | KEVIN BERBERYAN |
| Drywall Nailing | 11/13/2023 | Approved | JOHN HAYES |
| Final | 9/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/11/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 9/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |