13445 N GLADSTONE AVE 91342

Certificate Information: 13445 N GLADSTONE AVE 91342

Application / Permit
23014-20000-01203
Plan Check / Job No.
B23VN03882
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 13' X 18' TO AND CONVERT EXISTING DETACHED CARPORT TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/31/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 SELLA BENYAMIN
Corrections Issued 4/18/2023 SELLA BENYAMIN
Quality Review Completed 4/20/2023 STEVEN KIM
Building Plans Picked Up 4/24/2023 APPLICANT
Plan Check Approved 8/31/2023 SELLA BENYAMIN
Issued 8/31/2023 APPLICANT
CofO in Progress 5/20/2024 KEVIN BERBERYAN
No Progress 6/3/2024 ROBERT GOLD
CofO in Progress 6/3/2024 ROBERT GOLD
CofO Issued 9/10/2024 DANIEL ORRANTE
Permit Finaled 9/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/28/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 4/28/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/1/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 5/1/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/20/2023 Partial Inspection ROBERT GOLD
Footing/Foundation/Slab 9/20/2023 Partial Inspection KEVIN BERBERYAN
PLUMBING-Rough 9/20/2023 Partial Inspection KEVIN BERBERYAN
Pre-Inspection 9/20/2023 Partial Inspection KEVIN BERBERYAN
Footing/Foundation/Slab 10/13/2023 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 10/18/2023 Partial Inspection KEVIN BERBERYAN
Underground Mechanical 10/18/2023 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 10/24/2023 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Approved KEVIN BERBERYAN
Gas Test 11/13/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 11/20/2023 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 11/28/2023 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 11/28/2023 Approved KEVIN BERBERYAN
Green Building Rough 11/28/2023 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Rough 11/28/2023 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 11/28/2023 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 12/5/2023 Approved KEVIN BERBERYAN
Green Building Rough 12/5/2023 Approved KEVIN BERBERYAN
HVAC-Rough 12/5/2023 Approved KEVIN BERBERYAN
MERV13>=Rough 12/5/2023 Approved KEVIN BERBERYAN
PLUMBING-Rough 12/5/2023 Approved KEVIN BERBERYAN
Insulation 12/20/2023 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 12/20/2023 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 12/26/2023 Approved KEVIN BERBERYAN
Sewer 1/3/2024 Approved KEVIN BERBERYAN
Insulation 1/11/2024 Approved KEVIN BERBERYAN
Drywall Nailing 1/30/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 2/2/2024 Approved CHRISTOPHER ROJAS
Service/Power Release 2/14/2024 Not Ready for Inspection JOHN COLEMAN
Interior/Exterior Lathing 2/20/2024 No Access for Inspection CRAIG DAVIS
Interior/Exterior Lathing 2/27/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 3/19/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 3/19/2024 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 3/19/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 3/19/2024 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Final 3/19/2024 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Final 3/19/2024 Not Ready for Inspection KEVIN BERBERYAN
Pre-Inspection 3/19/2024 Partial Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 3/19/2024 Approved KEVIN BERBERYAN
Smoke Detectors 3/19/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 4/8/2024 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 4/8/2024 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Final 4/8/2024 Approved KEVIN BERBERYAN
PLUMBING-Final 4/8/2024 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 4/8/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 4/19/2024 Not Ready for Inspection ROBERT GOLD
Final 4/19/2024 Corrections Issued ROBERT GOLD
HVAC-Final 4/19/2024 Not Ready for Inspection ROBERT GOLD
PLUMBING-Final 4/19/2024 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Final 4/24/2024 Approved KEVIN BERBERYAN
Final 4/24/2024 Not Ready for Inspection KEVIN BERBERYAN
Grading Pre-Inspection 4/24/2024 Partial Inspection KEVIN BERBERYAN
Green Building Final 4/24/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 4/24/2024 Approved KEVIN BERBERYAN
PLUMBING-Final 4/24/2024 Approved KEVIN BERBERYAN
Service/Power Release 4/24/2024 Not Required KEVIN BERBERYAN
Final 5/20/2024 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 5/20/2024 Approved KEVIN BERBERYAN
Pre-Inspection 6/6/2024 Partial Inspection KEVIN BERBERYAN