11308 W SUNBURST ST 91342

Certificate Information: 11308 W SUNBURST ST 91342

Application / Permit
23014-20000-01194
Plan Check / Job No.
B23VN03845
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL, ADDITION OF 24'-11" X 59'9" IN REAR AND 38' 7" X 17' IN REAR WITH ATTACHED PATIO COVER AND ROOFTOP DECK TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT TO BE ISSUED AFTER 9/18/2023
Permit Issued
Issued on 10/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/31/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/3/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 4/5/2023 OMID HEDAYAT
Building Plans Picked Up 4/7/2023 APPLICANT
Plan Check Approved 9/13/2023 SEWADA ZADOORAN MILAGARDI
Issued 10/13/2023 APPLICANT
CofO in Progress 6/17/2025 MICHEL ABAJAN
Permit Finaled 6/20/2025 RUBEN SALAS
CofO Issued 6/20/2025 RUBEN SALAS
Permit Finaled 6/20/2025 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 4/14/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 4/17/2023 MEGAN GODINEZ
Hydrant and Access approval Cleared 5/2/2023 LAVEON RIDER
Grading Pre-Inspection Cleared 5/8/2023 ROBERT PINA
Low Impact Development (LID) Cleared 8/30/2023 SEWADA ZADOORAN MILAGARDI
Roof/Waste drainage to street Cleared 9/1/2023 MEGAN GODINEZ
GPI Written Notices Cleared 9/13/2023 SEWADA ZADOORAN MILAGA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/29/2023 Conditional Approval ROBERT GOLD
PLUMBING-Rough 11/30/2023 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 12/12/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/3/2024 Corrections Issued KEVIN BERBERYAN
Wood Frame 1/3/2024 Not Ready for Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Approved MICHEL ABAJAN
Pre-Inspection 2/15/2024 Partial Inspection MICHEL ABAJAN
Wood Frame 2/15/2024 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 3/18/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 3/18/2024 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 3/18/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 3/27/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/27/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 3/27/2024 Approved MICHEL ABAJAN
Insulation 4/5/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/5/2024 Approved MICHEL ABAJAN
Drywall Nailing 4/9/2024 Approved MICHEL ABAJAN
Shower Pan 5/24/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/19/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Final 10/16/2024 Approved MICHEL ABAJAN
Final 4/18/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 4/18/2025 Approved MICHEL ABAJAN
HVAC-Final 4/18/2025 Approved MICHEL ABAJAN
PLUMBING-Final 4/18/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 4/18/2025 Approved MICHEL ABAJAN
Final 6/16/2025 OK to Issue CofO MICHEL ABAJAN