11308 W SUNBURST ST 91342
Certificate Information: 11308 W SUNBURST ST 91342
- Application / Permit
- 23014-20000-01194
- Plan Check / Job No.
- B23VN03845
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL, ADDITION OF 24'-11" X 59'9" IN REAR AND 38' 7" X 17' IN REAR WITH ATTACHED PATIO COVER AND ROOFTOP DECK TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT TO BE ISSUED AFTER 9/18/2023
- Permit Issued
- Issued on 10/13/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/3/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 4/5/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 4/7/2023 | APPLICANT |
| Plan Check Approved | 9/13/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 10/13/2023 | APPLICANT |
| CofO in Progress | 6/17/2025 | MICHEL ABAJAN |
| Permit Finaled | 6/20/2025 | RUBEN SALAS |
| CofO Issued | 6/20/2025 | RUBEN SALAS |
| Permit Finaled | 6/20/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/14/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 5/2/2023 | LAVEON RIDER |
| Grading Pre-Inspection | Cleared | 5/8/2023 | ROBERT PINA |
| Low Impact Development (LID) | Cleared | 8/30/2023 | SEWADA ZADOORAN MILAGARDI |
| Roof/Waste drainage to street | Cleared | 9/1/2023 | MEGAN GODINEZ |
| GPI Written Notices | Cleared | 9/13/2023 | SEWADA ZADOORAN MILAGA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/29/2023 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 11/30/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/12/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2024 | Corrections Issued | KEVIN BERBERYAN |
| Wood Frame | 1/3/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 2/15/2024 | Partial Inspection | MICHEL ABAJAN |
| Wood Frame | 2/15/2024 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/18/2024 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 3/18/2024 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 3/18/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/27/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/27/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 3/27/2024 | Approved | MICHEL ABAJAN |
| Insulation | 4/5/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/5/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/9/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 5/24/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 10/16/2024 | Approved | MICHEL ABAJAN |
| Final | 4/18/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/18/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/18/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/18/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 4/18/2025 | Approved | MICHEL ABAJAN |
| Final | 6/16/2025 | OK to Issue CofO | MICHEL ABAJAN |