2910 S VINEYARD AVE 90016
Certificate Information: 2910 S VINEYARD AVE 90016
- Application / Permit
- 23014-20000-01186
- Plan Check / Job No.
- B23VN03833
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT(E) GARAGE AND ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | SERGIO MUNIZ |
| Corrections Issued | 4/1/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 4/18/2023 | APPLICANT |
| Plan Check Approved | 6/20/2023 | PINANK PATEL |
| Issued | 7/5/2023 | APPLICANT |
| CofO in Progress | 12/14/2023 | SCOTT FINNILA |
| CofO Issued | 12/14/2023 | DEROLD HAUFF |
| Permit Finaled | 12/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2023 | ANA SORIANO |
| Roof/Waste drainage to street | Cleared | 5/19/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2023 | ANA SORIANO |
| Sewer availability | Cleared | 5/25/2023 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Final | 8/10/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 8/10/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 8/11/2023 | Partial Approval | CALEB MEISTER |
| Deputy Drilled-In Anchors | 8/15/2023 | Conditional Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 8/17/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 9/14/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 9/14/2023 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 9/14/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 9/14/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 10/25/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 10/25/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 10/25/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 10/25/2023 | Approved | CALEB MEISTER |
| Insulation | 10/31/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 11/3/2023 | Approved | CALEB MEISTER |
| Gas Test | 11/27/2023 | Approved | JUSTIN HAWLEY |
| Final | 12/8/2023 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 12/8/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 12/8/2023 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 12/13/2023 | Approved | SCOTT FINNILA |
| Final | 12/13/2023 | OK to Issue CofO | SCOTT FINNILA |
| Green Building Final | 12/13/2023 | Approved | SCOTT FINNILA |
| HVAC-Final | 12/13/2023 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 12/13/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | SCOTT FINNILA |