1159 1/2 W 29TH ST 90007
Certificate Information: 1159 1/2 W 29TH ST 90007
- Application / Permit
- 23014-20000-01180
- Plan Check / Job No.
- B23VN03798
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- eplan New Attached 2-Story Accessory Dwelling Unit addition to existing 3-unit Apartment Building
- Permit Issued
- Issued on 8/22/2023
- Issuing Office
- Current Status
- CofO Issued on 4/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | PRANITA SHAH |
| Corrections Issued | 4/12/2023 | PRANITA SHAH |
| Quality Review Completed | 4/14/2023 | GARO TELMI |
| Applicant returned to address corrections | 7/21/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 8/16/2023 | PRANITA SHAH |
| Plan Check Approved | 8/21/2023 | PRANITA SHAH |
| Issued | 8/22/2023 | APPLICANT |
| CofO in Progress | 4/4/2025 | ALFREDO LOPEZ |
| Permit Finaled | 4/4/2025 | ERNESTO CORRAL |
| CofO Issued | 4/4/2025 | ERNESTO CORRAL |
| Permit Finaled | 4/4/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZI | Cleared | 4/13/2023 | MAYELA VILLA |
| Green Code | Cleared | 4/26/2023 | PRANITA SHAH |
| Address approval | Cleared | 5/4/2023 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 5/12/2023 | RUEL COLE |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2023 | JEANIE LAM |
| Sewer availability | Cleared | 6/6/2023 | JEANIE LAM |
| Low Impact Development (LID) | Cleared | 6/23/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 6/29/2023 | JEANIE LAM |
| Specific Plan | Cleared | 6/29/2023 | DANIEL MATA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/11/2023 | Partial Inspection | MARTIN TAVITIAN |
| METHANE-Barrier | 10/11/2023 | Partial Inspection | MARTIN TAVITIAN |
| METHANE-Subgrade | 10/11/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Deputy Drilled-In Anchors | 10/12/2023 | Partial Approval | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 10/16/2023 | Partial Inspection | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 11/2/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 11/2/2023 | No Access for Inspection | MARTIN TAVITIAN |
| METHANE-Barrier | 11/2/2023 | No Access for Inspection | MARTIN TAVITIAN |
| METHANE-Subgrade | 11/2/2023 | No Access for Inspection | MARTIN TAVITIAN |
| METHANE-Rough | 11/3/2023 | Approved | MARTIN TAVITIAN |
| Green Building Rough | 11/9/2023 | Approved | MARTIN TAVITIAN |
| Wood Frame | 11/9/2023 | Partial Approval | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Approved | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2023 | Approved | MARTIN TAVITIAN |
| Special/Order Compliance | 11/27/2023 | Partial Approval | MARTIN TAVITIAN |
| Special/Order Compliance | 11/28/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Deputy Wood Construction | 12/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Wood Frame | 3/28/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 4/3/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Insulation | 4/3/2024 | Approved | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 4/3/2024 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 4/8/2024 | Approved | ALFREDO LOPEZ |
| Final | 4/8/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 4/8/2024 | Partial Inspection | ALFREDO LOPEZ |
| Green Building Final | 4/8/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Barrier | 4/8/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Subgrade | 4/8/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/8/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 4/8/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 4/8/2024 | Approved | ALFREDO LOPEZ |
| Final | 8/6/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 8/6/2024 | Approved | ALFREDO LOPEZ |
| Green Building Final | 8/6/2024 | Approved | ALFREDO LOPEZ |
| METHANE-Barrier | 8/6/2024 | Approved | ALFREDO LOPEZ |
| METHANE-Subgrade | 8/6/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 8/6/2024 | Approved | ALFREDO LOPEZ |
| Final | 8/13/2024 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Final | 10/10/2024 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Final | 2/11/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Approved | ALFREDO LOPEZ |
| Final | 4/3/2025 | OK to Issue CofO | ALFREDO LOPEZ |