501 N CLIFFWOOD AVE 90049
Certificate Information: 501 N CLIFFWOOD AVE 90049
- Application / Permit
- 23014-20000-01159
- Plan Check / Job No.
- B23VN03744
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDIITONS AND REMODEL TO (E) SFD AND FOR A NEW 2-CAR GARAGE. ADD 12'-4" X 35'-2" FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/3/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | RAPHAEL ROSAS |
| Corrections Issued | 4/6/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 4/17/2023 | STEVEN KIM |
| Building Plans Picked Up | 4/18/2023 | APPLICANT |
| Applicant returned to address corrections | 5/8/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/27/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 8/22/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 8/30/2023 | RAPHAEL ROSAS |
| Issued | 10/3/2023 | APPLICANT |
| CofO in Progress | 8/20/2025 | KEVIN SARGSYAN |
| No Progress | 8/21/2025 | KEVIN SARGSYAN |
| CofO in Progress | 8/21/2025 | KEVIN SARGSYAN |
| CofO in Progress | 8/21/2025 | KEVIN SARGSYAN |
| CofO in Progress | 8/26/2025 | KEVIN SARGSYAN |
| Permit Finaled | 8/29/2025 | RICHARD STEINBACH |
| CofO Issued | 8/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2023 | JASON NG |
| Sewer availability | Cleared | 6/6/2023 | JASON NG |
| ZA Case | Cleared | 6/13/2023 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 6/13/2023 | NELSON RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 6/14/2023 | BRIAN MILLER |
| Low Impact Development (LID) | Cleared | 7/12/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 7/16/2023 | AHMED AMARRAGY |
| Construction near power lines | Cleared | 8/11/2023 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 8/22/2023 | RAPHAEL ROSAS |
| Address approval | Cleared | 8/28/2023 | DARIN LAM |
Contact Information
| Architect | Althaus,, Andrew Ernst; Lic. No.: C25002 | 31368 VIA COLINAS #105 WESTLAKE VILLAGE, CA 91362 |
| Contractor | Margolis Steven M Inc; Lic. No.: 688754-B | 3835 THOUSAND OAKS BLVD SUITE 200 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/13/2024 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 3/15/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/19/2024 | Partial Approval | KEVIN SARGSYAN |
| Special/Order Compliance | 4/1/2024 | Corrections Issued | KEVIN SARGSYAN |
| Wood Frame | 4/1/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 5/1/2024 | Conditional Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/14/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/18/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/2/2024 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 8/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Corrections Issued | CARLOS MATAMOROS |
| Wood Frame | 9/19/2024 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 11/1/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/1/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/6/2024 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 11/6/2024 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 11/6/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/6/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/25/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/25/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/25/2024 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 11/25/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/10/2024 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/23/2024 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 12/23/2024 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 12/23/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/22/2025 | Approved | KEVIN SARGSYAN |
| Insulation | 1/28/2025 | Approved | KEVIN SARGSYAN |
| Shower Pan | 1/28/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 2/5/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/10/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/16/2025 | Corrections Issued | KEVIN SARGSYAN |
| Service/Power Release | 6/16/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/20/2025 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 6/20/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Service/Power Release | 6/26/2025 | Approved | KENNETH NAGLE |
| HVAC-Final | 7/23/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 7/23/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Final | 7/25/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 7/25/2025 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 7/25/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 7/29/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 7/29/2025 | Approved | KEVIN SARGSYAN |
| Final | 8/20/2025 | OK to Issue CofO | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Approved | KEVIN SARGSYAN |