501 N CLIFFWOOD AVE 90049

Certificate Information: 501 N CLIFFWOOD AVE 90049

Application / Permit
23014-20000-01159
Plan Check / Job No.
B23VN03744
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDIITONS AND REMODEL TO (E) SFD AND FOR A NEW 2-CAR GARAGE. ADD 12'-4" X 35'-2" FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/3/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 RAPHAEL ROSAS
Corrections Issued 4/6/2023 RAPHAEL ROSAS
Quality Review Completed 4/17/2023 STEVEN KIM
Building Plans Picked Up 4/18/2023 APPLICANT
Applicant returned to address corrections 5/8/2023 RAPHAEL ROSAS
Applicant returned to address corrections 6/27/2023 RAPHAEL ROSAS
Applicant returned to address corrections 8/22/2023 RAPHAEL ROSAS
Plan Check Approved 8/30/2023 RAPHAEL ROSAS
Issued 10/3/2023 APPLICANT
CofO in Progress 8/20/2025 KEVIN SARGSYAN
No Progress 8/21/2025 KEVIN SARGSYAN
CofO in Progress 8/21/2025 KEVIN SARGSYAN
CofO in Progress 8/21/2025 KEVIN SARGSYAN
CofO in Progress 8/26/2025 KEVIN SARGSYAN
Permit Finaled 8/29/2025 RICHARD STEINBACH
CofO Issued 8/29/2025 RICHARD STEINBACH
Permit Finaled 8/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/6/2023 JASON NG
Sewer availability Cleared 6/6/2023 JASON NG
ZA Case Cleared 6/13/2023 NELSON RODRIGUEZ
ZA Case Cleared 6/13/2023 NELSON RODRIGUEZ
Grading Pre-Inspection Cleared 6/14/2023 BRIAN MILLER
Low Impact Development (LID) Cleared 7/12/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 7/16/2023 AHMED AMARRAGY
Construction near power lines Cleared 8/11/2023 RIDWAN HARDY
GPI Written Notices Cleared 8/22/2023 RAPHAEL ROSAS
Address approval Cleared 8/28/2023 DARIN LAM

Contact Information

Architect Althaus,, Andrew Ernst; Lic. No.: C25002 31368 VIA COLINAS #105      WESTLAKE VILLAGE, CA 91362
Contractor Margolis Steven M Inc; Lic. No.: 688754-B 3835 THOUSAND OAKS BLVD   SUITE 200    WESTLAKE VILLAGE, CA 91362
Engineer Judd,, Shane Dennis; Lic. No.: C70991 17 E HIGH ST STE A      MOORPARK, CA 93021

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/13/2024 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 3/15/2024 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 3/19/2024 Partial Approval KEVIN SARGSYAN
Special/Order Compliance 4/1/2024 Corrections Issued KEVIN SARGSYAN
Wood Frame 4/1/2024 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval KEVIN SARGSYAN
Deputy Steel/Welding 5/1/2024 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 6/14/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/18/2024 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/2/2024 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Corrections Issued KEVIN SARGSYAN
Verify Sprinkler Sign Off 8/16/2024 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2024 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Corrections Issued CARLOS MATAMOROS
Wood Frame 9/19/2024 Partial Approval CARLOS MATAMOROS
HVAC-Rough 11/1/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 11/1/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 11/6/2024 Corrections Issued KEVIN SARGSYAN
Gas Test 11/6/2024 Partial Approval KEVIN SARGSYAN
HVAC-Rough 11/6/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 11/6/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 11/25/2024 Approved KEVIN SARGSYAN
HVAC-Rough 11/25/2024 Approved KEVIN SARGSYAN
PLUMBING-Rough 11/25/2024 Approved KEVIN SARGSYAN
Underground Mechanical 11/25/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/10/2024 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 12/23/2024 Corrections Issued KEVIN SARGSYAN
Green Building Rough 12/23/2024 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 12/23/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 1/22/2025 Approved KEVIN SARGSYAN
Insulation 1/28/2025 Approved KEVIN SARGSYAN
Shower Pan 1/28/2025 Approved KEVIN SARGSYAN
Drywall Nailing 2/5/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/10/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Final 6/16/2025 Corrections Issued KEVIN SARGSYAN
Service/Power Release 6/16/2025 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 6/20/2025 Approved TEMISTOCLES CAAL
Service/Power Release 6/20/2025 Not Ready for Inspection TEMISTOCLES CAAL
Service/Power Release 6/26/2025 Approved KENNETH NAGLE
HVAC-Final 7/23/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 7/23/2025 Not Ready for Inspection KEVIN SARGSYAN
Green Building Final 7/25/2025 Approved KEVIN SARGSYAN
PLUMBING-Final 7/25/2025 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 7/25/2025 Approved KEVIN SARGSYAN
HVAC-Final 7/29/2025 Approved KEVIN SARGSYAN
PLUMBING-Final 7/29/2025 Approved KEVIN SARGSYAN
Final 8/20/2025 OK to Issue CofO KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Approved KEVIN SARGSYAN