4711 N PLACIDIA AVE 91602

Certificate Information: 4711 N PLACIDIA AVE 91602

Application / Permit
23014-20000-01148
Plan Check / Job No.
B23VN03717
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan - Addition And Remodeling To Existing SFD
Permit Issued
Issued on 10/9/2023
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 SAM CHANG
Corrections Issued 4/21/2023 SAM CHANG
Quality Review Completed 4/25/2023 EUGENE BARBEAU
Applicant returned to address corrections 7/5/2023 SAM CHANG
Plan Check Approved 7/7/2023 SAM CHANG
Issued 10/9/2023 APPLICANT
CofO in Progress 8/2/2024 JOSE AVILA
CofO in Progress 8/24/2024 JUAN VALENZUELA
No Progress 8/24/2024 JOSE AVILA
CofO Issued 11/13/2024 DANIEL ORRANTE
Permit Finaled 11/13/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/31/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 6/8/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/8/2023 CARLOS AGUILERA
Sewer availability Cleared 6/9/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/9/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 11/9/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 11/9/2023 Corrections Issued JOHN HAYES
Underground Mechanical 11/9/2023 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 11/22/2023 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/22/2023 Approved CHRISTOPHER ROJAS
Pre-Inspection 11/22/2023 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/11/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 12/11/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Inspection JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 12/29/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 1/19/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 1/19/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 1/19/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 1/24/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 2/27/2024 Partial Approval CRAIG DAVIS
Deputy Wood Construction 2/28/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 3/5/2024 Approved JOHN HAYES
Interior/Exterior Lathing 3/5/2024 Partial Approval JOHN HAYES
Shower Pan 3/6/2024 Approved JOHN HAYES
Insulation 3/8/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 3/15/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/20/2024 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 3/22/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/17/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 7/19/2024 Approved JOSE AVILA
Gas Test 7/19/2024 Approved JOSE AVILA
HVAC-Final 7/19/2024 Approved JOSE AVILA
PLUMBING-Final 7/19/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Approved JOSE AVILA
Final 8/2/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 8/2/2024 Approved JOSE AVILA
Smoke Detectors 8/2/2024 Approved JOSE AVILA
Special/Order Compliance 8/29/2024 Corrections Issued JOSE AVILA