427 N CARMELINA AVE 90049
Certificate Information: 427 N CARMELINA AVE 90049
- Application / Permit
- 23014-20000-01131
- Plan Check / Job No.
- B23VN03695
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND EXTERIOR FACADE WORK TO (E) SFD , CONVERT 18' X 8' PORTION OF EXISTING GARAGE TO PANTRY AND MUD ROOM, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | RARES BODEA |
| Corrections Issued | 4/3/2023 | RARES BODEA |
| Quality Review Completed | 4/5/2023 | STEVEN KIM |
| Building Plans Picked Up | 4/5/2023 | APPLICANT |
| Applicant returned to address corrections | 8/4/2023 | RARES BODEA |
| Applicant returned to address corrections | 2/14/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/9/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/15/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/21/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/28/2024 | RARES BODEA |
| Plan Check Approved | 6/6/2024 | RARES BODEA |
| Issued | 6/6/2024 | APPLICANT |
| CofO in Progress | 8/15/2025 | KEVIN SARGSYAN |
| Permit Finaled | 9/6/2025 | RICHARD STEINBACH |
| CofO Issued | 9/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| Permit | Cleared | 4/10/2023 | JASON NG |
| ZA Case | Cleared | 4/10/2023 | RUBEN VASQUEZ |
| Sewer availability | Cleared | 4/13/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | JASON NG |
| Distance to fire station | Cleared | 5/26/2023 | LAVEON RIDER |
| Hydrant and Access approval | Cleared | 5/26/2023 | LAVEON RIDER |
| Trees in Parkway | Cleared | 3/21/2024 | ADALBERTO VERA |
| Low Impact Development | Cleared | 4/3/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/8/2024 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/11/2024 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 5/21/2024 | RARES BODEA |
Contact Information
| Architect | Kenneth, J Ungar; Lic. No.: C21777 | , |
| Contractor | Tatum Construction Inc; Lic. No.: 733806-B | 1909 CENTINELA AVENUE SANTA MONICA, CA 90404 |
| Engineer | Tuchscher,, James; Lic. No.: C77649 | 5318 E 2ND ST., #539 LONG BEACH, CA 90803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/8/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/10/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 7/24/2024 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/29/2024 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/29/2024 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/1/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2024 | Approved | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 8/27/2024 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/13/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 9/18/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/20/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 9/20/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/20/2024 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 9/23/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/23/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 9/24/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/24/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/26/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 9/26/2024 | No Access for Inspection | KENNETH NAGLE |
| Deputy Reinf. Concrete | 9/26/2024 | No Access for Inspection | KENNETH NAGLE |
| Deputy Wood Construction | 9/26/2024 | No Access for Inspection | KENNETH NAGLE |
| Gas Test | 9/26/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 9/26/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/26/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/26/2024 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/2/2024 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 10/2/2024 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 10/2/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/4/2024 | Approved | KEVIN SARGSYAN |
| Insulation | 10/7/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 10/16/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/23/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/30/2025 | Approved | KEVIN SARGSYAN |
| Final | 4/30/2025 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 4/30/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 4/30/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 4/30/2025 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 4/30/2025 | Approved | KEVIN SARGSYAN |
| Final | 8/13/2025 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 8/15/2025 | OK to Issue CofO | KEVIN SARGSYAN |