427 N CARMELINA AVE 90049

Certificate Information: 427 N CARMELINA AVE 90049

Application / Permit
23014-20000-01131
Plan Check / Job No.
B23VN03695
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND EXTERIOR FACADE WORK TO (E) SFD , CONVERT 18' X 8' PORTION OF EXISTING GARAGE TO PANTRY AND MUD ROOM, ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/6/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 RARES BODEA
Corrections Issued 4/3/2023 RARES BODEA
Quality Review Completed 4/5/2023 STEVEN KIM
Building Plans Picked Up 4/5/2023 APPLICANT
Applicant returned to address corrections 8/4/2023 RARES BODEA
Applicant returned to address corrections 2/14/2024 RARES BODEA
Applicant returned to address corrections 5/9/2024 RARES BODEA
Applicant returned to address corrections 5/15/2024 RARES BODEA
Applicant returned to address corrections 5/21/2024 RARES BODEA
Applicant returned to address corrections 5/28/2024 RARES BODEA
Plan Check Approved 6/6/2024 RARES BODEA
Issued 6/6/2024 APPLICANT
CofO in Progress 8/15/2025 KEVIN SARGSYAN
Permit Finaled 9/6/2025 RICHARD STEINBACH
CofO Issued 9/6/2025 RICHARD STEINBACH
Permit Finaled 9/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
Permit Cleared 4/10/2023 JASON NG
ZA Case Cleared 4/10/2023 RUBEN VASQUEZ
Sewer availability Cleared 4/13/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 4/17/2023 JASON NG
Distance to fire station Cleared 5/26/2023 LAVEON RIDER
Hydrant and Access approval Cleared 5/26/2023 LAVEON RIDER
Trees in Parkway Cleared 3/21/2024 ADALBERTO VERA
Low Impact Development Cleared 4/3/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 4/8/2024 ANTHONY MAINEZ
Sewer availability Cleared 4/11/2024 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 5/21/2024 RARES BODEA

Contact Information

Architect Kenneth, J Ungar; Lic. No.: C21777       ,
Contractor Tatum Construction Inc; Lic. No.: 733806-B 1909 CENTINELA AVENUE      SANTA MONICA, CA 90404
Engineer Tuchscher,, James; Lic. No.: C77649 5318 E 2ND ST., #539      LONG BEACH, CA 90803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/8/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 7/10/2024 Partial Approval STEPHANIE SWANSON
Deputy Drilled-In Anchors 7/24/2024 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/29/2024 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 7/29/2024 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 8/1/2024 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Approved KEVIN SARGSYAN
Deputy Drilled-In Anchors 8/27/2024 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/27/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/13/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 9/18/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 9/20/2024 Approved KEVIN SARGSYAN
HVAC-Rough 9/20/2024 Approved KEVIN SARGSYAN
PLUMBING-Rough 9/20/2024 Corrections Issued KEVIN SARGSYAN
Gas Test 9/23/2024 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 9/23/2024 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 9/24/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 9/24/2024 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 9/26/2024 Not Ready for Inspection CARLOS MATAMOROS
Deputy Drilled-In Anchors 9/26/2024 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 9/26/2024 No Access for Inspection KENNETH NAGLE
Deputy Wood Construction 9/26/2024 No Access for Inspection KENNETH NAGLE
Gas Test 9/26/2024 Approved CARLOS MATAMOROS
Green Building Rough 9/26/2024 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 9/26/2024 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 9/26/2024 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 10/2/2024 Corrections Issued KEVIN SARGSYAN
Green Building Rough 10/2/2024 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 10/2/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 10/4/2024 Approved KEVIN SARGSYAN
Insulation 10/7/2024 Approved CARLOS MATAMOROS
Drywall Nailing 10/16/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 4/23/2025 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 4/30/2025 Approved KEVIN SARGSYAN
Final 4/30/2025 Corrections Issued KEVIN SARGSYAN
Green Building Final 4/30/2025 Approved KEVIN SARGSYAN
HVAC-Final 4/30/2025 Approved KEVIN SARGSYAN
PLUMBING-Final 4/30/2025 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 4/30/2025 Approved KEVIN SARGSYAN
Final 8/13/2025 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Approved KEVIN SARGSYAN
Final 8/15/2025 OK to Issue CofO KEVIN SARGSYAN