5865 N TOBIAS AVE 91411
Certificate Information: 5865 N TOBIAS AVE 91411
- Application / Permit
- 23014-20000-01116
- Plan Check / Job No.
- B23VN03626
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ADDITION OF 25'-0" X 19'-11' AT REAR OF (E) SFD. ALL WORK DONE PER WFPP. NFPA-13D FIRE SPRINKLER REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 3/25/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/28/2023 | APPLICANT |
| Applicant returned to address corrections | 4/14/2023 | MOHAMMAD ESMAILI |
| Issued | 4/17/2023 | APPLICANT |
| CofO in Progress | 9/27/2023 | RYAN SALAZAR |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 3/30/2023 | ROMAN GUTIERREZ |
| Low Impact Development (LID) | Cleared | 4/11/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/12/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/3/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 5/11/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 5/11/2023 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 5/12/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/31/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/2/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 6/14/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 6/14/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 6/27/2023 | Approved | RYAN SALAZAR |
| Insulation | 6/27/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/12/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/28/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/7/2023 | Approved | RYAN SALAZAR |
| Final | 9/7/2023 | No Access for Inspection | RYAN SALAZAR |
| Green Building Final | 9/7/2023 | No Access for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/7/2023 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 9/7/2023 | No Access for Inspection | RYAN SALAZAR |
| Final | 9/19/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 9/19/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 9/19/2023 | Approved | RYAN SALAZAR |
| Final | 9/26/2023 | OK to Issue CofO | RYAN SALAZAR |