10470 W LAURISTON AVE 90064
Certificate Information: 10470 W LAURISTON AVE 90064
- Application / Permit
- 23014-20000-01101
- Plan Check / Job No.
- B23VN03574
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 5' X 26' ADDITION AND INTERIOR REMODEL TO (E) SFD AT (E) KITCHEN, BATHROOM, LIVING ROOM, DINING ROOM, AND ENTRYWAY. ALL WORK PER DESIGN.
- Permit Issued
- Issued on 3/30/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2023 | OMAR GARNICA |
| Corrections Issued | 3/22/2023 | OMAR GARNICA |
| Plan Check Approved | 3/30/2023 | OMAR GARNICA |
| Issued | 3/30/2023 | APPLICANT |
| CofO in Progress | 9/9/2024 | STEPHANIE SWANSON |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
| CofO Issued | 9/16/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2023 | JASON NG |
| Roof/Waste drainage to street | Cleared | 3/23/2023 | JASON NG |
| Grading Pre-Inspection | Cleared | 3/24/2023 | KIRK LINKLATER |
| Specific Plan | Cleared | 3/28/2023 | PEDRO AYALA |
Contact Information
| Architect | Diaz,, Fred M; Lic. No.: C16477 | 533 FERNSHAW LA VERNE, CA 91750 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/3/2023 | Partial Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/9/2023 | Corrections Issued | BRENDAN LOONEY |
| METHANE-Barrier | 5/9/2023 | Approved | BRENDAN LOONEY |
| METHANE-Subgrade | 5/9/2023 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/16/2023 | Approved | BRENDAN LOONEY |
| Wood Frame | 6/6/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 6/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| Wood Frame | 6/13/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/16/2023 | Partial Approval | STEPHANIE SWANSON |
| Wood Frame | 6/23/2023 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/3/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/14/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/29/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/31/2023 | Conditional Approval | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 9/1/2023 | No Access for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 9/13/2023 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 9/13/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/15/2023 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 9/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/25/2023 | Conditional Approval | STEPHANIE SWANSON |
| HVAC-Rough | 9/25/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 9/25/2023 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 9/28/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 10/11/2023 | Approved | STEPHANIE SWANSON |
| Pre-Inspection | 3/19/2024 | Partial Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/22/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/31/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 6/27/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 6/27/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Final | 6/27/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Green Building Final | 6/27/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Green Building Rough | 6/27/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 6/27/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Final | 6/27/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 6/27/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 7/2/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 7/5/2024 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Final | 7/8/2024 | Approved | MICHAEL PELHAM |
| Service/Power Release | 7/8/2024 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 8/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 8/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 8/16/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 8/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 8/16/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 8/16/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/27/2024 | Approved | STEPHANIE SWANSON |
| Final | 8/27/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 8/27/2024 | Approved | STEPHANIE SWANSON |
| Final | 9/9/2024 | OK to Issue CofO | STEPHANIE SWANSON |