20023 W LONDELIUS ST 91324
Certificate Information: 20023 W LONDELIUS ST 91324
- Application / Permit
- 23014-20000-01097
- Plan Check / Job No.
- B23VN03570
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT EXISTING DETACHED GARAGE TO ADU WITH ADDITION PER ORDINANCE, ALL WORK PER WFPP
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- Current Status
- CofO Issued on 3/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2023 | MINA HABILI |
| Corrections Issued | 3/30/2023 | MINA HABILI |
| Applicant returned to address corrections | 10/4/2023 | MINA HABILI |
| Plan Check Approved | 10/12/2023 | NEHEMIAS RAMOS |
| Issued | 10/12/2023 | APPLICANT |
| CofO in Progress | 3/1/2024 | CHRIS CHRISTENSEN |
| Permit Finaled | 3/7/2024 | JOHN JANSON |
| CofO Issued | 3/7/2024 | JOHN JANSON |
| Permit Finaled | 3/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 5/19/2023 | DAGOVERTO GUERRERO |
| Construction within easement | Cleared | 8/31/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 9/6/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/17/2023 | Corrections Issued | JEFFREY HARTLINE |
| Underground Mechanical | 11/7/2023 | Approved | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Approved | JEFFREY HARTLINE |
| Sewer | 11/13/2023 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 12/8/2023 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 12/8/2023 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 12/8/2023 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 12/13/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 12/13/2023 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 12/13/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Insulation | 12/18/2023 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 12/18/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Drywall Nailing | 12/22/2023 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 12/22/2023 | Approved | JEFFREY HARTLINE |
| Grounding or Bonding | 12/27/2023 | Approved | MORRIS JACKSON |
| Underground Mechanical | 12/27/2023 | Approved | MORRIS JACKSON |
| Final | 2/20/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/20/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 2/20/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 2/20/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 2/23/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 2/23/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 2/29/2024 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 2/29/2024 | Approved | CHRIS CHRISTENSEN |