6845 N VANTAGE AVE 91605

Certificate Information: 6845 N VANTAGE AVE 91605

Application / Permit
23014-20000-01095
Plan Check / Job No.
B23VN03566
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DET 17'5"X20'9" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH 15'8"X8'0"ADDITION.
Permit Issued
Issued on 8/2/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/24/2023 HAYATO TSUCHIYA
Corrections Issued 3/29/2023 HAYATO TSUCHIYA
Building Plans Picked Up 3/31/2023 APPLICANT
Applicant returned to address corrections 7/24/2023 GIOVANNY CHAVEZ
Plan Check Approved 8/1/2023 JESSE ARELLANO
Issued 8/2/2023 APPLICANT
CofO in Progress 5/1/2025 GAREN HAYRAPETYAN
Permit Finaled 5/2/2025 RUBEN SALAS
CofO Issued 5/2/2025 RUBEN SALAS
Permit Finaled 5/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/22/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 4/22/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/25/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 4/25/2023 DAGOVERTO GUERRERO
Construction within easement Cleared 7/22/2023 TINA MIRANDA

Contact Information

Contractor La Green Development Inc; Lic. No.: 1061369-B 14530 HAMLIN STREET SUITE A      VAN NUYS, CA 91411
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/8/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 9/11/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 9/14/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/15/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 10/2/2023 Corrections Issued KIRK SANDERS
Green Building Rough 10/2/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 10/10/2023 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/24/2023 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 10/24/2023 Not Ready for Inspection ROBERT GOLD
Interior/Exterior Lathing 10/27/2023 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/30/2023 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 10/30/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/6/2023 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 11/6/2023 Corrections Issued CHRISTOPHER ROJAS
Insulation 11/6/2023 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/9/2023 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 11/9/2023 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/15/2023 Corrections Issued KIRK SANDERS
Green Building Rough 11/15/2023 Not Ready for Inspection KIRK SANDERS
Insulation 11/15/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 11/21/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 11/21/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 11/21/2023 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 11/21/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 11/29/2023 Approved KIRK SANDERS
Green Building Rough 11/29/2023 Approved KIRK SANDERS
HVAC-Rough 11/29/2023 Approved KIRK SANDERS
Insulation 11/29/2023 Approved KIRK SANDERS
Shower Pan 11/29/2023 Approved KIRK SANDERS
Drywall Nailing 12/5/2023 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 12/5/2023 Approved JOSE AVILA
Drywall Nailing 12/14/2023 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Final 7/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 7/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 7/23/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/23/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Final 4/11/2025 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 4/11/2025 Partial Approval OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/11/2025 SGSOV Not Ready OGANES TARAKHCHYAN
ELECTRICAL-Final 4/15/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 4/24/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 4/24/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/24/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Approved JENNIFER RABUCHIN
Final 4/28/2025 Corrections Issued WILLIAM WREN
Final 5/1/2025 OK to Issue CofO GAREN HAYRAPETYAN