22145 W VICTORY BLVD 91303
Certificate Information: 22145 W VICTORY BLVD 91303
- Application / Permit
- 23014-20000-01092
- Plan Check / Job No.
- B23VN03553
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'-2" x 18'-8" DETACHED GARAGE WITH AN ADDITION OF 15'-8" x 6'-9" TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER WFPP.
- Permit Issued
- Issued on 7/11/2023
- Issuing Office
- Current Status
- CofO Issued on 11/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 4/3/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 5/18/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 6/21/2023 | ISIS ARGUETA |
| Plan Check Approved | 7/6/2023 | GIOVANNY CHAVEZ |
| Issued | 7/11/2023 | APPLICANT |
| CofO in Progress | 11/20/2023 | TROY SANDERS |
| Permit Finaled | 11/30/2023 | JOHN JANSON |
| CofO Issued | 11/30/2023 | JOHN JANSON |
| Permit Finaled | 11/30/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2023 | FERNANDO GIL |
| Roof/Waste drainage to street | Cleared | 4/26/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2023 | FERNANDO GIL |
| ZI | Cleared | 6/20/2023 | NELSON RODRIGUEZ |
| Sewer availability | Cleared | 6/22/2023 | FERNANDO GIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2023 | Not Ready for Inspection | TROY SANDERS |
| Pre-Inspection | 7/31/2023 | Approved | TROY SANDERS |
| Pre-Inspection | 8/7/2023 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 8/9/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/11/2023 | Corrections Issued | HORACE FULTZ |
| Green Building Rough | 8/11/2023 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 8/15/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 10/4/2023 | Approved | TROY SANDERS |
| Final | 10/4/2023 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 10/4/2023 | Approved | TROY SANDERS |
| HVAC-Final | 10/4/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 10/4/2023 | Approved | TROY SANDERS |
| Service/Power Release | 10/4/2023 | Approved | TROY SANDERS |
| Smoke Detectors | 10/4/2023 | Approved | TROY SANDERS |
| Final | 11/20/2023 | OK to Issue CofO | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2023 | SGSOV Approved | TROY SANDERS |