6271 N BUFFALO AVE 91401
Certificate Information: 6271 N BUFFALO AVE 91401
- Application / Permit
- 23014-20000-01057
- Plan Check / Job No.
- B23VN03448
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD BUILDING TO BE FULLY SPRINKLERED BY NFPA 13D
- Permit Issued
- Issued on 11/3/2023
- Issuing Office
- Current Status
- CofO Issued on 2/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2023 | VICTOR CHEN |
| Corrections Issued | 3/30/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 9/8/2023 | FERNANDO FLORES |
| Plan Check Approved | 10/31/2023 | FERNANDO FLORES |
| Issued | 11/3/2023 | APPLICANT |
| CofO in Progress | 1/30/2026 | WAYNE REGESTER |
| Permit Finaled | 2/25/2026 | RUBEN SALAS |
| Permit Finaled | 2/25/2026 | RUBEN SALAS |
| CofO Issued | 2/25/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/25/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 10/13/2023 | TOMMY YIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: NA56881 | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/8/2024 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 5/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/9/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/28/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/8/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/26/2024 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 9/27/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 9/27/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 10/3/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 10/4/2024 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 10/4/2024 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 10/4/2024 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 10/4/2024 | Approved | GAREN HAYRAPETYAN |
| Insulation | 11/1/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/12/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 1/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 1/28/2025 | No Access for Inspection | GAREN HAYRAPETYAN |
| Shower Pan | 1/28/2025 | No Access for Inspection | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 1/30/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 1/30/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 6/9/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 6/9/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 6/9/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 6/9/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Final | 6/9/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Final | 6/9/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 6/9/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 6/26/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 8/1/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 8/11/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 8/15/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 12/31/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 1/8/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 1/29/2026 | OK to Issue CofO | WAYNE REGESTER |