736 3/4 E 74TH ST 90001

Certificate Information: 736 3/4 E 74TH ST 90001

Application / Permit
23014-20000-01048
Plan Check / Job No.
B23VN03436
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
24' 5" x 25' 0" ADDITION AND CONVERT EXISTING DETACHED 10'x16' GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). - PER WFPP
Permit Issued
Issued on 7/19/2023
Issuing Office
Current Status
CofO Issued on 10/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2023 APPLICANT
Assigned to Plan Check Engineer 3/24/2023 ISIS ARGUETA
Corrections Issued 3/25/2023 ISIS ARGUETA
Applicant returned to address corrections 6/13/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 6/26/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 7/10/2023 DANIEL ABRAMYAN
Plan Check Approved 7/19/2023 DANIEL ABRAMYAN
Issued 7/19/2023 APPLICANT
CofO in Progress 10/21/2024 MICHAEL LEWIS
CofO Issued 10/24/2024 RUBEN SALAS
Permit Finaled 10/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/24/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 4/24/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/25/2023 JEANIE LAM
Sewer availability Cleared 4/25/2023 JEANIE LAM
Community Plan Implem. Overlay Cleared 6/9/2023 HELEN JADALI
Roof/Waste drainage to street Cleared 6/14/2023 JEANIE LAM
Tenant Habitability Plan Cleared 6/22/2023 RICARDO BOHORQUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/16/2023 Approved JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 10/19/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 10/19/2023 Partial Approval MICHAEL LEWIS
Deputy Drilled-In Anchors 10/20/2023 Conditional Approval MICHAEL LEWIS
Footing/Foundation/Slab 10/23/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 11/6/2023 No Access for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 No Access for Inspection MICHAEL LEWIS
PLUMBING-Rough 11/6/2023 No Access for Inspection MICHAEL LEWIS
Underground Mechanical 1/11/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 2/20/2024 No Access for Inspection MICHAEL LEWIS
Wood Frame 2/20/2024 No Access for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Approved MICHAEL LEWIS
HVAC-Rough 3/8/2024 Not Ready for Inspection MICHAEL LEWIS
Interior/Exterior Lathing 3/8/2024 Not Ready for Inspection MICHAEL LEWIS
PLUMBING-Rough 3/12/2024 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 3/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 3/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/14/2024 No Access for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 No Access for Inspection MICHAEL LEWIS
HVAC-Rough 3/14/2024 No Access for Inspection MICHAEL LEWIS
Interior/Exterior Lathing 3/14/2024 No Access for Inspection MICHAEL LEWIS
PLUMBING-Rough 3/14/2024 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 3/15/2024 Not Ready for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Partial Inspection MICHAEL LEWIS
HVAC-Rough 3/15/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 3/15/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 3/15/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/19/2024 Conditional Approval MICHAEL LEWIS
ELECTRICAL-Rough 3/19/2024 Approved MICHAEL LEWIS
Green Building Rough 3/19/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 3/19/2024 Approved MICHAEL LEWIS
Insulation 3/22/2024 Partial Approval STUART CHAPMAN
Insulation 3/27/2024 No Access for Inspection JOSH MEISTER
Insulation 4/2/2024 Approved MICHAEL LEWIS
Drywall Nailing 4/5/2024 Not Ready for Inspection JOSH MEISTER
Shower Pan 4/5/2024 Not Ready for Inspection JOSH MEISTER
Drywall Nailing 4/9/2024 Corrections Issued MICHAEL LEWIS
Shower Pan 4/9/2024 Corrections Issued MICHAEL LEWIS
Drywall Nailing 4/10/2024 Corrections Issued MICHAEL LEWIS
Drywall Nailing 4/15/2024 Corrections Issued MICHAEL LEWIS
Shower Pan 4/15/2024 Corrections Issued MICHAEL LEWIS
Drywall Nailing 5/3/2024 Not Ready for Inspection JOSH MEISTER
Drywall Nailing 5/7/2024 Not Ready for Inspection MICHAEL LEWIS
Drywall Nailing 8/19/2024 Approved MICHAEL LEWIS
Shower Pan 8/19/2024 Approved MICHAEL LEWIS
Underground Mechanical 8/19/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/28/2024 Approved MICHAEL LEWIS
Final 8/28/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 8/28/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 9/17/2024 Approved MICHAEL LEWIS
Final 9/17/2024 Partial Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 9/17/2024 Approved MICHAEL LEWIS
Smoke Detectors 9/17/2024 Approved MICHAEL LEWIS
Final 10/18/2024 OK to Issue CofO MICHAEL LEWIS