8240 N MORSE AVE 91605

Certificate Information: 8240 N MORSE AVE 91605

Application / Permit
23014-20000-01042
Plan Check / Job No.
B23VN03424
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Addition at rear and remodel existing 1-story single family dwelling, replace front porch, trellis addition, enclose (E) rear patio; SFD to be sprinklered throughout
Permit Issued
Issued on 4/5/2024
Issuing Office
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/29/2023 VICTOR CHEN
Corrections Issued 3/30/2023 VICTOR CHEN
Applicant returned to address corrections 3/13/2024 MINA HABILI
Applicant returned to address corrections 4/2/2024 MINA HABILI
Plan Check Approved 4/3/2024 MINA HABILI
Issued 4/5/2024 APPLICANT
CofO in Progress 8/26/2025 VINCENT HANLEY
Permit Finaled 9/11/2025 RUBEN SALAS
CofO Issued 9/11/2025 RUBEN SALAS
Permit Finaled 9/11/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 10/25/2023 MELINEH AGHAKHABIAN
Eng Process Fee Ord 176,300 Cleared 3/13/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/13/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/19/2024 Approved GREGG CUMMINGS
Footing/Foundation/Slab 4/19/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 5/14/2024 Partial Approval DAVID ANDERSON
Sewer 5/14/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 No Access for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Partial Approval GREGG CUMMINGS
Insulation 5/20/2024 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval VINCENT HANLEY
PLUMBING-Rough 6/12/2024 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 8/16/2024 Corrections Issued GREGG CUMMINGS
HVAC-Rough 8/16/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 8/16/2024 Approved GREGG CUMMINGS
ELECTRICAL-Rough 8/23/2024 Approved GREGG CUMMINGS
HVAC-Rough 8/23/2024 Approved GREGG CUMMINGS
Wood Frame 8/23/2024 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 8/26/2024 Approved GREGG CUMMINGS
Green Building Rough 8/26/2024 Approved GREGG CUMMINGS
Insulation 9/3/2024 Approved DAVID MATSON
Interior/Exterior Lathing 9/3/2024 Partial Approval DAVID MATSON
Drywall Nailing 9/10/2024 Approved GAREN HAYRAPETYAN
Shower Pan 11/8/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 6/4/2025 Corrections Issued VINCENT HANLEY
Final 6/4/2025 Corrections Issued VINCENT HANLEY
Green Building Final 6/4/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved VINCENT HANLEY
Smoke Detectors 6/4/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 7/8/2025 Approved VINCENT HANLEY
Final 7/8/2025 Corrections Issued VINCENT HANLEY
HVAC-Final 7/8/2025 Approved VINCENT HANLEY
PLUMBING-Final 7/8/2025 Approved VINCENT HANLEY
Service/Power Release 7/8/2025 Approved VINCENT HANLEY
Final 8/26/2025 OK to Issue CofO VINCENT HANLEY