8403-8405 N BARDWELL AVE 91402

Certificate Information: 8403-8405 N BARDWELL AVE 91402

Application / Permit
23014-20000-01040
Plan Check / Job No.
B23VN03411
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ATTACHED ACCESSORY DWELLING UNIT 12'-0" X 22'-0" PER LAMC 12.22 A.33(c) and (e), (N) IRREGULAR SHAPED 10'-0" X 10-8" ATTACHED COVERED PATIONON REAR SIDE OF ADU. "COMPLY WITH DEPARTMENT ORDER effective date 02/16/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2023 APPLICANT
Assigned to Plan Check Engineer 3/22/2023 JESSE ARELLANO
Corrections Issued 3/23/2023 JESSE ARELLANO
Building Plans Picked Up 3/24/2023 APPLICANT
Applicant returned to address corrections 3/30/2023 RAMA DABADGE
Plan Check Approved 4/6/2023 ALEC MOUSAKHANIAN
Issued 4/6/2023 APPLICANT
CofO in Progress 12/14/2023 LUCIANO GAUNA
Permit Finaled 5/8/2024 DAVID JAMES
CofO Issued 5/8/2024 DAVID JAMES
Permit Finaled 5/8/2024 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 3/30/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/30/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 3/30/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 3/30/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Moraga Builders And Design; Lic. No.: 567115-B 8436 BARDWELL AVENUE      PANORAMA, CA 91402
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/10/2023 Corrections Issued MICKEY YAMASHITA
Deputy Drilled-In Anchors 4/12/2023 Conditional Approval MICKEY YAMASHITA
Footing/Foundation/Slab 4/12/2023 Corrections Issued MICKEY YAMASHITA
Underground Mechanical 4/13/2023 Not Ready for Inspection MICKEY YAMASHITA
BUILDING-Rough-Frame 4/17/2023 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 4/17/2023 Corrections Issued MICKEY YAMASHITA
Deputy Wood Construction 5/18/2023 Conditional Approval LUCIANO GAUNA
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Approved LUCIANO GAUNA
Shower Pan 5/24/2023 Approved LUCIANO GAUNA
BUILDING-Rough-Frame 5/31/2023 Approved LUCIANO GAUNA
ELECTRICAL-Rough 5/31/2023 Approved LUCIANO GAUNA
Green Building Rough 5/31/2023 Approved LUCIANO GAUNA
HVAC-Rough 5/31/2023 Approved LUCIANO GAUNA
PLUMBING-Rough 5/31/2023 Approved LUCIANO GAUNA
Drywall Nailing 6/6/2023 Approved LUCIANO GAUNA
Gas Test 6/6/2023 Approved LUCIANO GAUNA
Insulation 6/6/2023 Approved LUCIANO GAUNA
Interior/Exterior Lathing 6/6/2023 Approved LUCIANO GAUNA
ELECTRICAL-Final 7/18/2023 Approved LUCIANO GAUNA
Final 7/18/2023 Partial Approval LUCIANO GAUNA
Footing/Foundation/Slab 7/18/2023 Approved LUCIANO GAUNA
Green Building Final 7/18/2023 Approved LUCIANO GAUNA
HVAC-Final 7/18/2023 Approved LUCIANO GAUNA
PLUMBING-Final 7/18/2023 Approved LUCIANO GAUNA
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Approved LUCIANO GAUNA
Smoke Detectors 7/18/2023 Approved LUCIANO GAUNA