10275 N BARTEE AVE 91331
Certificate Information: 10275 N BARTEE AVE 91331
- Application / Permit
- 23014-20000-01002
- Plan Check / Job No.
- B23VN03254
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX 20'X28' DET GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33 (c) & (d) WITH 20'X30' ADDITION & ALL NEW ROOF FRAMING. ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/3/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 3/18/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 4/5/2023 | APPLICANT |
| Applicant returned to address corrections | 6/28/2023 | OMAR GARNICA |
| Applicant returned to address corrections | 6/30/2023 | ISIS ARGUETA |
| Plan Check Approved | 7/3/2023 | ISIS ARGUETA |
| Issued | 7/3/2023 | APPLICANT |
| CofO in Progress | 12/15/2023 | JENNIFER RABUCHIN |
| No Progress | 3/7/2024 | ROBERT GOLD |
| CofO in Progress | 3/7/2024 | ROBERT GOLD |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 4/17/2023 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 5/25/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/30/2023 | COLIN LOREDO |
Contact Information
| Contractor | Vicsinc.Com; Lic. No.: 1002544-B | P O BOX 950931 MISSION HILLS, CA 91395 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/10/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 7/10/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 7/10/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 7/10/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/10/2023 | Partial Approval | JENNIFER RABUCHIN |
| Pre-Inspection | 7/10/2023 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/18/2023 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 7/18/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 8/4/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 8/4/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 8/4/2023 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 8/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/18/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 8/18/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 8/18/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/18/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/18/2023 | Partial Approval | RAUL OLAGI |
| MERV13>=Rough | 8/18/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 8/18/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 8/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 8/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 8/24/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/24/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/24/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 8/24/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/7/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| Final | 11/7/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 11/7/2023 | Approved | JENNIFER RABUCHIN |