10275 N BARTEE AVE 91331

Certificate Information: 10275 N BARTEE AVE 91331

Application / Permit
23014-20000-01002
Plan Check / Job No.
B23VN03254
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX 20'X28' DET GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33 (c) & (d) WITH 20'X30' ADDITION & ALL NEW ROOF FRAMING. ALL WORK PER WFPP.
Permit Issued
Issued on 7/3/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2023 APPLICANT
Assigned to Plan Check Engineer 3/17/2023 HAYATO TSUCHIYA
Corrections Issued 3/18/2023 HAYATO TSUCHIYA
Building Plans Picked Up 4/5/2023 APPLICANT
Applicant returned to address corrections 6/28/2023 OMAR GARNICA
Applicant returned to address corrections 6/30/2023 ISIS ARGUETA
Plan Check Approved 7/3/2023 ISIS ARGUETA
Issued 7/3/2023 APPLICANT
CofO in Progress 12/15/2023 JENNIFER RABUCHIN
No Progress 3/7/2024 ROBERT GOLD
CofO in Progress 3/7/2024 ROBERT GOLD
Permit Finaled 4/10/2024 RUBEN SALAS
CofO Issued 4/10/2024 RUBEN SALAS
Permit Finaled 4/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/14/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/17/2023 COLIN LOREDO
Sewer availability Cleared 4/17/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 5/25/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/30/2023 COLIN LOREDO

Contact Information

Contractor Vicsinc.Com; Lic. No.: 1002544-B P O BOX 950931      MISSION HILLS, CA 91395

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/10/2023 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 7/10/2023 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 7/10/2023 Approved JENNIFER RABUCHIN
METHANE-Rough 7/10/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 7/10/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/10/2023 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 7/10/2023 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 7/18/2023 Approved JENNIFER RABUCHIN
Pre-Inspection 7/18/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/4/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 8/4/2023 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 8/4/2023 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 8/4/2023 Partial Approval JENNIFER RABUCHIN
Wood Frame 8/4/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/18/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 8/18/2023 Approved RAUL OLAGI
Green Building Rough 8/18/2023 Approved RAUL OLAGI
HVAC-Rough 8/18/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 8/18/2023 Partial Approval RAUL OLAGI
MERV13>=Rough 8/18/2023 Approved RAUL OLAGI
PLUMBING-Rough 8/18/2023 Approved RAUL OLAGI
Drywall Nailing 8/22/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 8/22/2023 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 8/24/2023 Approved JENNIFER RABUCHIN
Insulation 8/24/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/24/2023 Approved JENNIFER RABUCHIN
Shower Pan 8/24/2023 Approved JENNIFER RABUCHIN
Service/Power Release 9/7/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 11/7/2023 Approved JENNIFER RABUCHIN
Final 11/7/2023 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 11/7/2023 Approved JENNIFER RABUCHIN
HVAC-Final 11/7/2023 Approved JENNIFER RABUCHIN
MERV13>=Final 11/7/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/7/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/7/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 11/7/2023 Approved JENNIFER RABUCHIN
Smoke Detectors 11/7/2023 Approved JENNIFER RABUCHIN