7303 N TYRONE AVE 91405
Certificate Information: 7303 N TYRONE AVE 91405
- Application / Permit
- 23014-20000-01000
- Plan Check / Job No.
- B23VN03245
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DET 20'X18' GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH IRR 42'5-1/4"X28'-0" ADDITION AND ALL NEW ROOF FRAMING PER ENGR DESIGN.
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 3/17/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 3/31/2023 | APPLICANT |
| Plan Check Approved | 6/7/2023 | ALEC MOUSAKHANIAN |
| Issued | 6/7/2023 | APPLICANT |
| CofO in Progress | 9/11/2024 | VINCENT HANLEY |
| Permit Finaled | 9/25/2024 | DANIEL ORRANTE |
| CofO Issued | 9/25/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/25/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/12/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | MEGAN GODINEZ |
| Low Impact Development (LID) | Cleared | 5/23/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/23/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sin,, John Paul; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/15/2023 | Not Ready for Inspection | DAVID MATSON |
| Gas Test | 6/15/2023 | Not Ready for Inspection | DAVID MATSON |
| Sewer | 6/15/2023 | Not Ready for Inspection | DAVID MATSON |
| Underground Mechanical | 6/15/2023 | Not Ready for Inspection | DAVID MATSON |
| Gas Test | 6/22/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 6/22/2023 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 6/28/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 6/28/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/3/2023 | Approved | MATTHEW NELSON |
| Pre-Inspection | 7/10/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/8/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 9/8/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 9/8/2023 | Corrections Issued | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 9/8/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/14/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/14/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 9/14/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/14/2023 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 9/14/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 9/18/2023 | Conditional Approval | DAVID MATSON |
| Wood Frame | 9/19/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 9/20/2023 | Conditional Approval | DAVID MATSON |
| Green Building Rough | 9/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Special/Order Compliance | 9/20/2023 | Corrections Issued | GREGG CUMMINGS |
| Deputy Wood Construction | 9/21/2023 | Conditional Approval | DAVID MATSON |
| Wood Frame | 9/22/2023 | No Access for Inspection | THOMAS FINNILA |
| Drywall Nailing | 10/5/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 10/5/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 10/5/2023 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/5/2023 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 10/13/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 10/13/2023 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 10/13/2023 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 10/19/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 10/19/2023 | Approved | MISAEL ESPARZA |
| Insulation | 10/19/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 11/27/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/4/2023 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/13/2024 | Approved | MATTHEW NELSON |
| Final | 8/13/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/13/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 8/13/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 8/28/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 8/28/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 8/28/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 9/4/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/4/2024 | Approved | VINCENT HANLEY |
| Final | 9/4/2024 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 9/4/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/4/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Approved | VINCENT HANLEY |
| Final | 9/11/2024 | OK to Issue CofO | VINCENT HANLEY |