19440 W HARTLAND ST 91335

Certificate Information: 19440 W HARTLAND ST 91335

Application / Permit
23014-20000-00999
Plan Check / Job No.
B23VN03243
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. (N) Detached 2-story ADU
Permit Issued
Issued on 7/31/2023
Issuing Office
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 HERNAN ARREOLA
Corrections Issued 4/12/2023 HERNAN ARREOLA
Quality Review Completed 4/19/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 7/28/2023 HERNAN ARREOLA
Issued 7/31/2023 APPLICANT
CofO in Progress 5/21/2025 ARUTYUN MADATYAN
Permit Finaled 6/5/2025 JOHN JANSON
CofO Issued 6/5/2025 JOHN JANSON
Permit Finaled 6/5/2025 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 5/22/2023 WALTER RAMIREZ
Low Impact Development (LID) Cleared 6/22/2023 TOMMY YIN
Address approval Cleared 6/29/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 6/29/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 6/30/2023 ROMAN GUTIERREZ
Sewer availability Cleared 6/30/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/13/2023 Partial Approval JEFFREY BULL
Excavation/Setback/Form/Re-Bar 10/19/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval JEFFREY BULL
Green Building Rough 12/6/2023 Not Ready for Inspection JEFFREY BULL
Verify Sprinkler Sign Off 12/6/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 2/1/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 2/1/2024 Approved JEFFREY BULL
Green Building Rough 2/1/2024 Approved JEFFREY BULL
HVAC-Rough 2/1/2024 Approved JEFFREY BULL
PLUMBING-Rough 2/1/2024 Approved JEFFREY BULL
Insulation 3/4/2024 Corrections Issued JEFFREY BULL
Drywall Nailing 3/26/2024 Approved HENRY KIM
Insulation 3/26/2024 Approved HENRY KIM
Interior/Exterior Lathing 3/26/2024 Approved HENRY KIM
Shower Pan 3/26/2024 Approved HENRY KIM
ELECTRICAL-Rough 4/29/2024 Approved JEFFREY BULL
Service/Power Release 4/29/2024 Approved JEFFREY BULL
ELECTRICAL-Final 9/6/2024 Approved JEFFREY BULL
Final 9/6/2024 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 9/6/2024 Approved JEFFREY BULL
Green Building Final 9/6/2024 Not Ready for Inspection JEFFREY BULL
HVAC-Final 9/6/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Final 9/6/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 9/6/2024 Approved JEFFREY BULL
Final 5/21/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 5/21/2025 Approved ARUTYUN MADATYAN
Service/Power Release 5/21/2025 Not Required ARUTYUN MADATYAN