19031 W BASSETT ST 91335
Certificate Information: 19031 W BASSETT ST 91335
- Application / Permit
- 23014-20000-00996
- Plan Check / Job No.
- B23VN03234
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan. Convert (E) Garage to (N) Bedroom + Add (N) Bathroom to be apart of (E) SFD. Addition of attached New Carport
- Permit Issued
- Issued on 4/19/2023
- Issuing Office
- Current Status
- CofO Issued on 12/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2023 | JOSEPH RAFOLS |
| Corrections Issued | 3/23/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 4/4/2023 | KHUONG TRUONG |
| Plan Check Approved | 4/19/2023 | KHUONG TRUONG |
| Issued | 4/19/2023 | APPLICANT |
| CofO in Progress | 10/31/2023 | JEFFREY BULL |
| CofO Issued | 12/12/2023 | JOHN JANSON |
| Permit Finaled | 12/12/2023 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 3/23/2023 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 3/30/2023 | RYAN KIM |
| Sewer availability | Cleared | 3/30/2023 | RYAN KIM |
| Low Impact Development (LID) | Cleared | 4/13/2023 | ROGELIO CORTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/4/2023 | Conditional Approval | JEFFREY BULL |
| Underground Mechanical | 5/4/2023 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 5/8/2023 | Corrections Issued | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 5/9/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/2/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 6/2/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 6/2/2023 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 6/2/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 6/2/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 6/6/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 6/6/2023 | Approved | JEFFREY BULL |
| Shower Pan | 6/6/2023 | Approved | JEFFREY BULL |
| Insulation | 6/8/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 6/9/2023 | Approved | JEFFREY BULL |
| Final | 7/17/2023 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 7/17/2023 | Approved | JEFFREY BULL |
| Green Building Final | 7/17/2023 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 7/17/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 7/17/2023 | Approved | JEFFREY BULL |
| Final | 10/23/2023 | No Access for Inspection | HENRY KIM |
| Green Building Final | 10/23/2023 | No Access for Inspection | HENRY KIM |
| Final | 10/31/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 10/31/2023 | Approved | JEFFREY BULL |