14915-14917 W SANDRA ST 91345

Certificate Information: 14915-14917 W SANDRA ST 91345

Application / Permit
23014-20000-00978
Plan Check / Job No.
B23VN03187
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
8'7" X 15'5" ADDITION AND CONVERT IRREGULARLY SHAPED 22'11" X 28'1" PORTION OF EXISTING SFD (370 SF) INTO (N) SB9 UNIT (493 SF) PER SB9 Two-Unit Development CA Govt Code 65852.21. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 10/4/2023
Issuing Office
Current Status
CofO Issued on 8/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2023 APPLICANT
Assigned to Plan Check Engineer 3/20/2023 GURUNATH NESARAJAH
Corrections Issued 3/21/2023 GURUNATH NESARAJAH
Applicant returned to address corrections 6/8/2023 GURUNATH NESARAJAH
Applicant returned to address corrections 7/7/2023 ROSENDO MEDINA
Applicant returned to address corrections 7/10/2023 ROSENDO MEDINA
Applicant returned to address corrections 8/4/2023 MADISON ODELL
Applicant returned to address corrections 9/25/2023 MADISON ODELL
Plan Check Approved 9/29/2023 MADISON ODELL
Issued 10/4/2023 APPLICANT
CofO in Progress 7/24/2024 JENNIFER RABUCHIN
Permit Finaled 8/7/2024 RUBEN SALAS
CofO Issued 8/7/2024 RUBEN SALAS
Permit Finaled 8/7/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/9/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 5/9/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 6/1/2023 ROMAN GUTIERREZ
Sewer availability Cleared 6/1/2023 ROMAN GUTIERREZ
Senate Bill 9 Cleared 9/6/2023 NELSON RODRIGUEZ
Low Impact Development (LID) Cleared 9/13/2023 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Keshishian,, Anthony; Lic. No.: C89551 2654 RISA D      GLENDALE, CA 91208

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/27/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/3/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/3/2024 Partial Approval JENNIFER RABUCHIN
Green Building Rough 1/3/2024 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 1/3/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/21/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/21/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 2/21/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 2/21/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/21/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/29/2024 Approved JOHN COLEMAN
ELECTRICAL-Rough 2/29/2024 Approved JOHN COLEMAN
Green Building Rough 2/29/2024 Approved JOHN COLEMAN
Interior/Exterior Lathing 2/29/2024 Approved JOHN COLEMAN
Insulation 4/4/2024 Approved JENNIFER RABUCHIN
Shower Pan 4/17/2024 Corrections Issued SALVADOR MARTINEZ
Shower Pan 4/19/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 4/24/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/24/2024 Approved JENNIFER RABUCHIN
Final 6/24/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 6/24/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 6/24/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/1/2024 Approved JENNIFER RABUCHIN
Final 7/1/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 7/1/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/1/2024 Approved JENNIFER RABUCHIN
Final 7/25/2024 OK to Issue CofO JENNIFER RABUCHIN