11335 W DELANO ST 91606

Certificate Information: 11335 W DELANO ST 91606

Application / Permit
23014-20000-00964
Plan Check / Job No.
B23VN03128
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16'-3"x24'-3",14'-4"x10'-10" ADDITION TO & REMODEL SFD
Permit Issued
Issued on 4/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2023 APPLICANT
Assigned to Plan Check Engineer 3/17/2023 SERGIO MUNIZ
Corrections Issued 3/18/2023 SERGIO MUNIZ
Building Plans Picked Up 3/21/2023 APPLICANT
Issued 4/17/2023 APPLICANT
CofO in Progress 9/21/2023 JOHN HAYES
Permit Finaled 1/23/2024 RUBEN SALAS
CofO Issued 1/23/2024 RUBEN SALAS
Permit Finaled 1/23/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/24/2023 LEE GUILBEAUX
Sewer availability Cleared 3/24/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 4/11/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 4/11/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/25/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 4/25/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 5/1/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 5/13/2023 Partial Approval KEVIN SARGSYAN
Green Building Rough 5/13/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 5/13/2023 Partial Approval KEVIN SARGSYAN
Underground Mechanical 5/13/2023 Off-Hour Fees Due
Insulation 5/17/2023 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Partial Approval JOHN HAYES
Deputy Wood Construction 6/9/2023 Conditional Approval JOHN HAYES
BUILDING-Rough-Frame 6/21/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/21/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 6/21/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/21/2023 Approved JENNIFER RABUCHIN
Sewer 6/21/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/28/2023 Approved JOHN HAYES
Interior/Exterior Lathing 6/28/2023 Partial Approval JOHN HAYES
Insulation 7/3/2023 Approved RAUL OLAGI
Shower Pan 7/3/2023 Approved RAUL OLAGI
Drywall Nailing 7/10/2023 Approved JOHN HAYES
Interior/Exterior Lathing 7/10/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 9/18/2023 Approved JOHN HAYES
ELECTRICAL-Final 9/18/2023 Approved JOHN HAYES
Final 9/18/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 9/18/2023 Approved JOHN HAYES
Green Building Final 9/18/2023 Approved JOHN HAYES
Green Building Rough 9/18/2023 Approved JOHN HAYES
HVAC-Final 9/18/2023 Approved JOHN HAYES
PLUMBING-Final 9/18/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/18/2023 SGSOV Approved JOHN HAYES
Service/Power Release 9/18/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 9/18/2023 Approved JOHN HAYES
ELECTRICAL-Final 9/21/2023 Approved JOHN HAYES
Final 9/21/2023 OK to Issue CofO JOHN HAYES
HVAC-Final 9/21/2023 Approved JOHN HAYES
PLUMBING-Final 9/21/2023 Approved JOHN HAYES
Service/Power Release 9/21/2023 Approved JOHN HAYES