- **ePlan** Addition and Alteration to (E) SF.D., scope of work to include: New Master Bedroom, New Master Bathroom, Relocate Windows And Door,New Covered Patio
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Current Status
- CofO Issued on 7/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2023 | AMY GUEVARRA |
| Corrections Issued | 3/23/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 4/20/2023 | AMY GUEVARRA |
| Plan Check Approved | 8/2/2023 | EDWIN ESPIN |
| No Progress | 8/4/2023 | EDWIN ESPIN |
| Plan Check Approved | 8/4/2023 | EDWIN ESPIN |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 6/26/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 7/5/2024 | RUBEN SALAS |
| CofO Issued | 7/5/2024 | RUBEN SALAS |
| Permit Finaled | 7/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/26/2023 | MELINEH AGHAKHABIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/27/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/27/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/30/2024 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 1/30/2024 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 1/30/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/31/2024 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 1/31/2024 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Approved | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 3/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 3/11/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/15/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 3/15/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 3/18/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 3/21/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/21/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 3/21/2024 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 4/4/2024 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 4/10/2024 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/10/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/16/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 4/16/2024 | Approved | JENNIFER RABUCHIN |
| Final | 5/2/2024 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Final | 6/25/2024 | Approved | JENNIFER RABUCHIN |
| Final | 6/25/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/25/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 6/25/2024 | Approved | JENNIFER RABUCHIN |