16246-16248 W SEPTO ST 91343
Certificate Information: 16246-16248 W SEPTO ST 91343
- Application / Permit
- 23014-20000-00928
- Plan Check / Job No.
- B23VN03034
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan 2ND STORY ADDITION AND CONVERSION OF (E) GARAGE TO ADU, ATTACHED TO (E) SFD. ATTACHED ADU PER LAMC 12.22 A.33 (c) and (e).
- Permit Issued
- Issued on 11/11/2023
- Issuing Office
- Current Status
- CofO Issued on 7/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | ADRIANA LOPEZ |
| Corrections Issued | 4/28/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 5/18/2023 | QUAN NGHIEM |
| Applicant returned to address corrections | 8/4/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 11/9/2023 | ADRIANA LOPEZ |
| Issued | 11/11/2023 | APPLICANT |
| CofO in Progress | 6/13/2024 | JAVIER RAMOS JR |
| Permit Finaled | 7/5/2024 | RUBEN SALAS |
| CofO Issued | 7/5/2024 | RUBEN SALAS |
| Permit Finaled | 7/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 5/15/2023 | FERNANDO GIL |
| Grading Pre-Inspection | Cleared | 5/22/2023 | SERGIO VALENZUELA |
| Low Impact Development (LID) | Cleared | 7/7/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 7/12/2023 | FERNANDO GIL |
| GPI Written Notices | Cleared | 11/9/2023 | ADRIANA LOPEZ |
Contact Information
| Contractor | D G Builders Inc; Lic. No.: 1067237-B | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/4/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/15/2023 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 12/15/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/8/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Wood Construction | 2/13/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | ROBERT GOLD |
| PLUMBING-Rough | 2/16/2024 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 2/23/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/23/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 2/23/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/23/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/23/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/26/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/27/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Insulation | 2/27/2024 | Conditional Approval | SALVADOR MARTINEZ |
| Drywall Nailing | 3/1/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 3/1/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/5/2024 | Approved | JAVIER RAMOS JR |
| Final | 4/5/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 4/5/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/5/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/5/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/5/2024 | Approved | JAVIER RAMOS JR |
| Final | 6/13/2024 | OK to Issue CofO | JAVIER RAMOS JR |