10954 N GERALD AVE 91344
Certificate Information: 10954 N GERALD AVE 91344
- Application / Permit
- 23014-20000-00889
- Plan Check / Job No.
- B23VN02888
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ****ePlan**** 2nd floor addition (329 sf) and conversion of (e) det garage (329 sf) to an ADU (658 sf) per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 12/19/2023
- Issuing Office
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | REZA HAGHIGHAT |
| Corrections Issued | 3/22/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 3/31/2023 | KAVIAN REFAHI |
| Plan Check Approved | 12/11/2023 | REZA HAGHIGHAT |
| Issued | 12/19/2023 | APPLICANT |
| CofO in Progress | 4/16/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
| CofO Issued | 4/24/2025 | RUBEN SALAS |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Permit | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/17/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 8/25/2023 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/30/2024 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 3/4/2024 | Approved | JAVIER RAMOS JR |
| Sewer | 5/17/2024 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 6/26/2024 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/28/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/28/2024 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 7/24/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 8/21/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/9/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/23/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/23/2024 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 9/23/2024 | Partial Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 9/23/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/30/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/30/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/30/2024 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 9/30/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/30/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/11/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 10/11/2024 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 1/30/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/13/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/13/2025 | Corrections Issued | JAVIER RAMOS JR |
| Service/Power Release | 2/13/2025 | Approved | JAVIER RAMOS JR |
| Gas Test | 2/18/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/18/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/28/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 4/3/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/3/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 4/3/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 4/3/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 4/9/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 4/9/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 4/15/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 4/15/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |