11325 W MARTHA ST 91601
Certificate Information: 11325 W MARTHA ST 91601
- Application / Permit
- 23014-20000-00887
- Plan Check / Job No.
- B23VN02882
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW SECOND FLOOR ADU ADDITION TO (E) 2-CAR GARAGE per ordinance LAMC 12.22 A.33 (c)-(d)NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 2/14/2025
- Issuing Office
- Current Status
- CofO Issued on 4/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | JAD BASMA |
| Corrections Issued | 3/23/2023 | JAD BASMA |
| Quality Review Completed | 3/30/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/29/2024 | JAD BASMA |
| Applicant returned to address corrections | 9/9/2024 | JAD BASMA |
| Applicant returned to address corrections | 12/24/2024 | JAD BASMA |
| Applicant returned to address corrections | 1/30/2025 | JAD BASMA |
| Plan Check Approved | 2/12/2025 | JAD BASMA |
| Issued | 2/14/2025 | APPLICANT |
| CofO in Progress | 3/27/2026 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 4/29/2026 | RUBEN SALAS |
| CofO Issued | 4/29/2026 | RUBEN SALAS |
| Permit Finaled | 4/29/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/23/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/26/2024 | BIAINA HARITUNIAN |
Contact Information
| Architect | Boorboor,, Mehdi; Lic. No.: NA33900 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/14/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 5/14/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/2/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/27/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 8/27/2025 | Partial Inspection | JOSE AVILA |
| HVAC-Rough | 9/25/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/26/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/4/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 12/4/2025 | Approved | JOSE AVILA |
| Green Building Rough | 12/4/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/12/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 12/12/2025 | Approved | JOSE AVILA |
| Insulation | 12/16/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 12/26/2025 | Approved | CHRISTOPHER MORFIN |
| Interior/Exterior Lathing | 1/5/2026 | Approved | JOSE AVILA |
| Special/Order Compliance | 1/5/2026 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 2/9/2026 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/13/2026 | Approved | MICHAEL CORTEZ |
| Final | 3/13/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 3/13/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 3/13/2026 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/13/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 3/24/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |