11325 W MARTHA ST 91601

Certificate Information: 11325 W MARTHA ST 91601

Application / Permit
23014-20000-00887
Plan Check / Job No.
B23VN02882
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW SECOND FLOOR ADU ADDITION TO (E) 2-CAR GARAGE per ordinance LAMC 12.22 A.33 (c)-(d)NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 2/14/2025
Issuing Office
Current Status
CofO Issued on 4/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 JAD BASMA
Corrections Issued 3/23/2023 JAD BASMA
Quality Review Completed 3/30/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 1/29/2024 JAD BASMA
Applicant returned to address corrections 9/9/2024 JAD BASMA
Applicant returned to address corrections 12/24/2024 JAD BASMA
Applicant returned to address corrections 1/30/2025 JAD BASMA
Plan Check Approved 2/12/2025 JAD BASMA
Issued 2/14/2025 APPLICANT
CofO in Progress 3/27/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 4/29/2026 RUBEN SALAS
CofO Issued 4/29/2026 RUBEN SALAS
Permit Finaled 4/29/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/23/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 4/23/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/26/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/26/2024 BIAINA HARITUNIAN

Contact Information

Architect Boorboor,, Mehdi; Lic. No.: NA33900       ,
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Inspection 5/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/2/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 8/27/2025 Approved JOSE AVILA
PLUMBING-Rough 8/27/2025 Partial Inspection JOSE AVILA
HVAC-Rough 9/25/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 9/26/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 12/4/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 12/4/2025 Approved JOSE AVILA
Green Building Rough 12/4/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 12/12/2025 Approved JOSE AVILA
PLUMBING-Rough 12/12/2025 Approved JOSE AVILA
Insulation 12/16/2025 Approved JOSE AVILA
Drywall Nailing 12/26/2025 Approved CHRISTOPHER MORFIN
Interior/Exterior Lathing 1/5/2026 Approved JOSE AVILA
Special/Order Compliance 1/5/2026 Corrections Issued JOSE AVILA
Pre-Inspection 2/9/2026 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 2/13/2026 Approved MICHAEL CORTEZ
Final 3/13/2026 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 3/13/2026 Approved GAREN HAYRAPETYAN
Green Building Final 3/13/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 3/13/2026 Approved GAREN HAYRAPETYAN
Final 3/24/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ