15954 W RAYEN ST 91343

Certificate Information: 15954 W RAYEN ST 91343

Application / Permit
23014-20000-00882
Plan Check / Job No.
B23VN02875
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan EXISTING GARAGE CONVERSION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 5/18/2023
Issuing Office
Current Status
CofO Issued on 2/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2023 APPLICANT
Assigned to Plan Check Engineer 3/13/2023 MOHAMMAD ESMAILI
Corrections Issued 3/14/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 5/2/2023 MOHAMMAD ESMAILI
Plan Check Approved 5/16/2023 JOE VO
Issued 5/18/2023 APPLICANT
CofO in Progress 1/17/2024 RAUL OLAGI
Permit Finaled 2/9/2024 RUBEN SALAS
Permit Finaled 2/9/2024 RUBEN SALAS
CofO Issued 2/9/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 3/16/2023 WALTER RAMIREZ
Address approval Cleared 3/17/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 3/20/2023 FERNANDO GIL
Sewer availability Cleared 3/20/2023 FERNANDO GIL
Low Impact Development (LID) Cleared 4/6/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/1/2023 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/9/2023 Corrections Issued RAUL OLAGI
Special/Order Compliance 6/9/2023 Corrections Issued RAUL OLAGI
Deputy Drilled-In Anchors 6/12/2023 Conditional Approval RAUL OLAGI
PLUMBING-Rough 6/13/2023 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 6/13/2023 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/15/2023 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 6/16/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/10/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 8/10/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval RAUL OLAGI
HVAC-Rough 8/10/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 8/10/2023 Corrections Issued RAUL OLAGI
Special/Order Compliance 8/10/2023 Corrections Issued RAUL OLAGI
Underground Mechanical 8/10/2023 Partial Approval RAUL OLAGI
Insulation 8/17/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 8/28/2023 Corrections Issued RAUL OLAGI
Insulation 8/28/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 8/28/2023 Partial Approval RAUL OLAGI
Rough-Elec/Plmb/HVAC 8/28/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 9/25/2023 Approved RAUL OLAGI
Drywall Nailing 9/25/2023 Approved RAUL OLAGI
Green Building Rough 9/25/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 10/3/2023 Approved RAUL OLAGI
Shower Pan 10/3/2023 Corrections Issued RAUL OLAGI
Special/Order Compliance 10/3/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 10/11/2023 Approved RAUL OLAGI
Shower Pan 10/11/2023 Approved RAUL OLAGI
Underground Mechanical 11/1/2023 Approved RAUL OLAGI
ELECTRICAL-Final 1/9/2024 Approved RAUL OLAGI
Final 1/9/2024 Corrections Issued RAUL OLAGI
Green Building Final 1/9/2024 Approved RAUL OLAGI
HVAC-Final 1/9/2024 Approved RAUL OLAGI
PLUMBING-Final 1/9/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 1/9/2024 Approved RAUL OLAGI
Final 1/17/2024 OK to Issue CofO RAUL OLAGI