17040 W MOONCREST DR 91436

Certificate Information: 17040 W MOONCREST DR 91436

Application / Permit
23014-20000-00865
Plan Check / Job No.
B23VN02802
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE EXISTING SINGLE FAMILY DWELLING EXCEPT 1'-10" OF WALL TO REMAIN; REBUILD 89'-4" X 68'-7" SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/25/2023
Issuing Office
Current Status
CofO Issued on 11/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 SELLA BENYAMIN
Corrections Issued 3/21/2023 SELLA BENYAMIN
Quality Review Completed 3/30/2023 STEVEN KIM
Building Plans Picked Up 3/30/2023 APPLICANT
Plan Check Approved 5/25/2023 SELLA BENYAMIN
Issued 5/25/2023 APPLICANT
CofO in Progress 11/14/2024 MORRIS JACKSON
Permit Finaled 11/22/2024 JOHN JANSON
CofO Issued 11/22/2024 JOHN JANSON
Permit Finaled 11/22/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/28/2023 LEE GUILBEAUX
Sewer availability Cleared 3/28/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 5/19/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/22/2023 LEE GUILBEAUX
GPI Written Notices Cleared 5/25/2023 SELLA BENYAMIN
Grading Pre-Inspection Cleared 5/25/2023 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/28/2023 Corrections Issued SEAN HAUPT
PLUMBING-Rough 6/28/2023 Not Ready for Inspection SEAN HAUPT
Excavation/Setback/Form/Re-Bar 7/3/2023 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 7/3/2023 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 7/5/2023 No Access for Inspection VINCENT HANLEY
PLUMBING-Rough 7/5/2023 No Access for Inspection VINCENT HANLEY
Deputy Drilled-In Anchors 7/11/2023 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 7/11/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 7/11/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/8/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Partial Approval VINCENT HANLEY
Green Building Rough 8/8/2023 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 8/8/2023 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 9/6/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 9/11/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 9/11/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 10/17/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Approved VINCENT HANLEY
HVAC-Rough 10/17/2023 Approved VINCENT HANLEY
PLUMBING-Rough 10/17/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 11/6/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/6/2023 Partial Approval VINCENT HANLEY
Insulation 11/9/2023 Approved VINCENT HANLEY
Drywall Nailing 11/20/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/20/2023 Partial Approval VINCENT HANLEY
Shower Pan 1/2/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/19/2024 Conditional Approval SEAN HAUPT
Interior/Exterior Lathing 1/24/2024 Approved VINCENT HANLEY
Service/Power Release 1/24/2024 Approved VINCENT HANLEY
PLUMBING-Final 4/26/2024 Corrections Issued VINCENT HANLEY
Deck 8/16/2024 Corrections Issued THOMAS FINNILA
Grounding or Bonding 8/16/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 10/4/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 10/4/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 10/4/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 10/17/2024 Approved THOMAS FINNILA
Final 10/17/2024 Corrections Issued THOMAS FINNILA
Green Building Rough 10/17/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/17/2024 SGSOV Not Ready THOMAS FINNILA
Verify Sprinkler Sign Off 10/17/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 10/23/2024 Approved THOMAS FINNILA
HVAC-Final 10/23/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Final 10/23/2024 Approved THOMAS FINNILA
Final 11/13/2024 OK to Issue CofO MORRIS JACKSON
Green Building Final 11/13/2024 Approved MORRIS JACKSON
HVAC-Final 11/13/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Approved MORRIS JACKSON
Smoke Detectors 11/13/2024 Approved MORRIS JACKSON