17611 W HAYNES ST 91406
Certificate Information: 17611 W HAYNES ST 91406
- Application / Permit
- 23014-20000-00832
- Plan Check / Job No.
- B23VN02698
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: conversion of existing detached garage to ADU plus addition to ADU per LAMC 12.22 A.33 (c)-(d) ***SEE COMMENTS***
- Permit Issued
- Issued on 4/3/2023
- Issuing Office
- Current Status
- CofO Issued on 9/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2023 | DANIEL SMILEY |
| Corrections Issued | 3/16/2023 | DANIEL SMILEY |
| Plan Check Approved | 4/2/2023 | KHUONG TRUONG |
| Plan Check Approved | 4/3/2023 | KHUONG TRUONG |
| Issued | 4/3/2023 | APPLICANT |
| CofO in Progress | 8/31/2023 | JON MCHUGH |
| Permit Finaled | 9/1/2023 | JOHN JANSON |
| Permit Finaled | 9/1/2023 | JOHN JANSON |
| CofO Issued | 9/1/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 3/17/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 3/20/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 3/20/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 3/20/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 3/20/2023 | MEGAN GODINEZ |
| ZI | Cleared | 3/21/2023 | STEVEN WECHSLER |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/27/2023 | Conditional Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 4/28/2023 | Corrections Issued | JOHN KIDWELL |
| PLUMBING-Rough | 4/28/2023 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/1/2023 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 5/4/2023 | Approved | SEAN HAUPT |
| Underground Mechanical | 5/10/2023 | Partial Approval | JON MCHUGH |
| Sewer | 5/15/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 6/5/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 6/5/2023 | Corrections Issued | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 6/12/2023 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 6/16/2023 | Partial Approval | SEAN WIRCH |
| Insulation | 6/21/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 6/27/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 6/27/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 6/27/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/27/2023 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 6/27/2023 | Approved | JUSTIN HAWLEY |
| Shower Pan | 6/27/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 7/5/2023 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 7/5/2023 | Approved | JON MCHUGH |
| Shower Pan | 7/5/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 7/28/2023 | Not Ready for Inspection | HORACE FULTZ |
| Final | 7/28/2023 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Final | 7/28/2023 | Approved | HORACE FULTZ |
| HVAC-Final | 7/28/2023 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Final | 7/28/2023 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | HORACE FULTZ |
| Smoke Detectors | 7/28/2023 | Corrections Issued | HORACE FULTZ |
| ELECTRICAL-Final | 8/14/2023 | Corrections Issued | JON MCHUGH |
| Final | 8/14/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 8/14/2023 | Corrections Issued | JON MCHUGH |
| Smoke Detectors | 8/14/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 8/23/2023 | Corrections Issued | JON MCHUGH |
| Smoke Detectors | 8/23/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 8/25/2023 | Corrections Issued | JON MCHUGH |
| Smoke Detectors | 8/25/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 8/30/2023 | Approved | JON MCHUGH |
| Final | 8/30/2023 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 8/30/2023 | Approved | JON MCHUGH |