8037 N MASON AVE 91306

Certificate Information: 8037 N MASON AVE 91306

Application / Permit
23014-20000-00808
Plan Check / Job No.
B23VN02635
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 24'-10" x 16'-4" ADDITION AND ENLCOSE (E) 12'-6" X 10'-10" PATIO COVER TO MAKE A (N) DEN FOR THE (E) SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 3/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 JESSE ARELLANO
Corrections Issued 3/2/2023 JESSE ARELLANO
Applicant returned to address corrections 3/6/2023 LUISANGEL VALENZUELA
Plan Check Approved 3/7/2023 SERGIO MUNIZ
Issued 3/7/2023 APPLICANT
CofO in Progress 7/1/2025 TROY SANDERS
CofO Issued 8/22/2025 JOHN JANSON
Permit Finaled 8/22/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/6/2023 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 3/6/2023 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/7/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/23/2024 Approved ALEXANDER HANDY
ELECTRICAL-Rough 12/9/2024 Not Ready for Inspection ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 12/9/2024 Approved ALEXANDER HANDY
PLUMBING-Rough 12/9/2024 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 12/18/2024 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Rough 12/18/2024 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Approved ALEXANDER HANDY
Green Building Rough 12/18/2024 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 1/3/2025 Corrections Issued MORRIS JACKSON
Gas Test 1/3/2025 Approved MORRIS JACKSON
Insulation 1/3/2025 Partial Approval MORRIS JACKSON
Interior/Exterior Lathing 1/3/2025 Partial Approval MORRIS JACKSON
Rough-Elec/Plmb/HVAC 1/3/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 1/7/2025 Corrections Issued ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Approved ALEXANDER HANDY
Green Building Rough 1/7/2025 Approved ALEXANDER HANDY
Insulation 1/7/2025 Partial Approval ALEXANDER HANDY
Interior/Exterior Lathing 1/7/2025 Partial Approval ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 1/7/2025 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 1/10/2025 Partial Inspection JOHN COLEMAN
Shower Pan 1/10/2025 Approved JOHN COLEMAN
Insulation 1/23/2025 Approved ALEXANDER HANDY
Drywall Nailing 1/28/2025 Approved ALEXANDER HANDY
Shower Pan 1/28/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 3/21/2025 Not Ready for Inspection DAVID SCANTLIN
Final 3/21/2025 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 3/21/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 3/21/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 3/21/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 6/30/2025 Approved TROY SANDERS
Final 6/30/2025 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 6/30/2025 Approved TROY SANDERS
Green Building Final 6/30/2025 Not Ready for Inspection TROY SANDERS
Final 7/1/2025 OK to Issue CofO TROY SANDERS
Green Building Final 7/1/2025 Approved TROY SANDERS