19100 W VICTORY BLVD 91335
Certificate Information: 19100 W VICTORY BLVD 91335
- Application / Permit
- 23014-20000-00803
- Plan Check / Job No.
- B23VN02624
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: MAJOR REMODEL AND 2ND STORY ADDITION AND 2 CAR GARAGE ADDITION TO (E) 1 STORY SFD AT FRONT BUILDING. *** BUILDING TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGH OUT***
- Permit Issued
- Issued on 6/5/2025
- Issuing Office
- Current Status
- Issued on 6/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 3/22/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 4/20/2023 | QUAN NGHIEM |
| Applicant returned to address corrections | 9/25/2023 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 1/16/2025 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 2/4/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 2/10/2025 | CRYSTEL MAALOUF |
| Issued | 6/5/2025 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/3/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 7/6/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2023 | TAL SHEMEN |
| ZI | Cleared | 7/31/2023 | ALEX VELA |
| Sewer availability | Cleared | 8/15/2024 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arutyunyan,, Vladimir; Lic. No.: C92714 | 331 ARDEN AVE SUIT 201 GLENDALE, CA 91203 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/11/2025 | Partial Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 8/27/2025 | Approved | JON MCHUGH |
| Deputy Wood Construction | 10/30/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Corrections Issued | JON MCHUGH |
| Deputy Wood Construction | 1/15/2026 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 1/15/2026 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2026 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 1/15/2026 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 1/15/2026 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 1/29/2026 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 1/29/2026 | Approved | JON MCHUGH |
| Green Building Rough | 1/29/2026 | Approved | JON MCHUGH |
| HVAC-Rough | 1/29/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 1/29/2026 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 1/29/2026 | Approved | JON MCHUGH |
| Insulation | 2/13/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 2/13/2026 | Approved | JON MCHUGH |
| Shower Pan | 2/13/2026 | Approved | JON MCHUGH |
| Drywall Nailing | 2/27/2026 | Approved | JON MCHUGH |
| Underground Mechanical | 3/19/2026 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 5/1/2026 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Final | 5/28/2026 | Not Ready for Inspection | JON MCHUGH |
| Gas Test | 5/28/2026 | Approved | JON MCHUGH |
| HVAC-Final | 5/28/2026 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 5/28/2026 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 6/16/2026 | Approved | SEAN WIRCH |
| HVAC-Final | 6/16/2026 | Not Ready for Inspection | SEAN WIRCH |
| PLUMBING-Final | 6/16/2026 | Not Ready for Inspection | SEAN WIRCH |
| Service/Power Release | 6/16/2026 | Approved | SEAN WIRCH |