22857-22859 W VOSE ST 91307

Certificate Information: 22857-22859 W VOSE ST 91307

Application / Permit
23014-20000-00802
Plan Check / Job No.
B23VN02616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 17' X 17'8" ATTACHED CARPORT AND (N) 13'6" X 16'10" IRREGULARLY SHAPED ADDITION (221 SF) TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). (N) 9'2" X 6'4" IRREGULARLY SHAPED ADDITION (57 SF) AND (N) 5'5" X 6'10" PORCH TO (E) SINGLE FAMILY DWELLING. WORK TO BE DONE PER ENGINEERING.
Permit Issued
Issued on 6/27/2023
Issuing Office
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/7/2023 EDWIN ESPIN
Corrections Issued 3/9/2023 EDWIN ESPIN
Applicant returned to address corrections 4/26/2023 MADISON ODELL
Plan Check Approved 6/13/2023 MADISON ODELL
Issued 6/27/2023 APPLICANT
CofO in Progress 4/16/2024 JEFFREY HARTLINE
Permit Finaled 4/23/2024 JOHN JANSON
CofO Issued 4/23/2024 JOHN JANSON
Permit Finaled 4/23/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/12/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/12/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/12/2023 LEE GUILBEAUX
Sewer availability Cleared 4/12/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Mobed,, Ashkan; Lic. No.: C92493 23450 KITTREDGE ST      WEST HILLS, CA 91307

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2023 Approved JEFFREY HARTLINE
Sewer 10/17/2023 Approved JEFFREY HARTLINE
Insulation 10/25/2023 Partial Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 12/20/2023 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 12/20/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/11/2024 Approved JEFFREY HARTLINE
Green Building Rough 1/11/2024 Approved JEFFREY HARTLINE
HVAC-Rough 1/11/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/11/2024 Partial Approval JEFFREY HARTLINE
Insulation 1/18/2024 Approved JEFFREY HARTLINE
Drywall Nailing 1/23/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/29/2024 Approved JEFFREY HARTLINE
Shower Pan 1/29/2024 Approved JEFFREY HARTLINE
Final 4/3/2024 Corrections Issued JEFFREY HARTLINE
Green Building Final 4/3/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/3/2024 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 4/3/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 4/15/2024 Approved JEFFREY HARTLINE
Final 4/15/2024 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 4/15/2024 Approved JEFFREY HARTLINE
PLUMBING-Final 4/15/2024 Approved JEFFREY HARTLINE