4845 N BELLINGHAM AVE 91607

Certificate Information: 4845 N BELLINGHAM AVE 91607

Application / Permit
23014-20000-00801
Plan Check / Job No.
B23VN02615
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONVERT (E) PROTION OF GARAGE TO ACCESSORY DWELLING UNIT AND CONVERT (E) GREEN HOUSE TO LAUNDRY ROOM WITH SMALL ADDITION, AND ACCESSORY DWELLING UNIT ADDITION PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/11/2023
Issuing Office
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 SUNMIN LEE
Corrections Issued 3/18/2023 SUNMIN LEE
Quality Review Completed 3/21/2023 GARO TELMI
Applicant returned to address corrections 8/3/2023 SUNMIN LEE
Applicant returned to address corrections 8/23/2023 SUNMIN LEE
Plan Check Approved 9/7/2023 DANIEL YIP
Issued 9/11/2023 APPLICANT
CofO in Progress 2/12/2024 JOSE AVILA
Permit Finaled 7/24/2024 RUBEN SALAS
CofO Issued 7/24/2024 RUBEN SALAS
Permit Finaled 7/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/22/2023 MEGAN GODINEZ
Specific Plan Cleared 4/12/2023 JOANNA MARROQUIN
Specific Plan Cleared 4/12/2023 JOANNA MARROQUIN
Eng Process Fee Ord 176,300 Cleared 4/17/2023 MEGAN GODINEZ
Miscellaneous Cleared 5/1/2023 NELSON RODRIGUEZ
Low Impact Development (LID) Cleared 6/13/2023 ROGELIO CORTES
Sewer availability Cleared 6/14/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 7/12/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 8/25/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Barragan,, Pedro; Lic. No.: C90531 329 N HUBBARD AVE      SAN FERNANDO, CA 91340

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/13/2023 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 9/18/2023 Corrections Issued CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 9/21/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/25/2023 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 10/2/2023 Corrections Issued KIRK SANDERS
Underground Mechanical 10/5/2023 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 10/11/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Corrections Issued KIRK SANDERS
Green Building Rough 10/23/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Corrections Issued KIRK SANDERS
Green Building Rough 11/14/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 11/21/2023 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Partial Approval JUAN VALENZUELA
Green Building Rough 11/21/2023 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 11/30/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 11/30/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 11/30/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 12/5/2023 Corrections Issued KIRK SANDERS
HVAC-Rough 12/5/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 12/5/2023 Partial Approval KIRK SANDERS
PLUMBING-Rough 12/5/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 12/11/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 12/11/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 12/18/2023 Corrections Issued JOSE AVILA
Green Building Rough 12/18/2023 Approved JOSE AVILA
HVAC-Rough 12/18/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 12/21/2023 Approved JOSE AVILA
Drywall Nailing 12/26/2023 Corrections Issued JOSE AVILA
Insulation 12/26/2023 Approved JOSE AVILA
Drywall Nailing 12/29/2023 Corrections Issued JOSE AVILA
Drywall Nailing 1/16/2024 Approved JOSE AVILA
Interior/Exterior Lathing 1/16/2024 Approved JOSE AVILA
ELECTRICAL-Final 2/8/2024 Corrections Issued JOSE AVILA
HVAC-Final 2/8/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 2/8/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 2/9/2024 Approved JOSE AVILA
Final 2/9/2024 OK to Issue CofO JOSE AVILA
Green Building Final 2/9/2024 Approved JOSE AVILA
HVAC-Final 2/9/2024 Approved JOSE AVILA
PLUMBING-Final 2/9/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Approved JOSE AVILA
Service/Power Release 2/9/2024 Approved JOSE AVILA
Smoke Detectors 2/9/2024 Approved JOSE AVILA