10019-10021 N TOPEKA DR 91324

Certificate Information: 10019-10021 N TOPEKA DR 91324

Application / Permit
23014-20000-00791
Plan Check / Job No.
B23VN02551
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19'5" X 21'5" GARAGE AND (N) 14'3" X 28'10" ADDITION TO (N) ACCESSORY DWELLING UNIT (799 SF) PER LAMC 12.22 A.33(c) and (e). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 6/16/2023
Issuing Office
Current Status
CofO Issued on 4/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/6/2023 MADISON ODELL
Corrections Issued 3/7/2023 MADISON ODELL
Applicant returned to address corrections 3/25/2023 MADISON ODELL
Plan Check Approved 3/30/2023 MADISON ODELL
Issued 6/16/2023 APPLICANT
CofO in Progress 4/11/2025 DAVID SCANTLIN
Permit Finaled 4/14/2025 JOHN JANSON
CofO Issued 4/14/2025 JOHN JANSON
Permit Finaled 4/14/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/9/2023 FERNANDO GIL
Roof/Waste drainage to street Cleared 3/9/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 3/13/2023 FERNANDO GIL
Sewer availability Cleared 3/13/2023 FERNANDO GIL
ZA Case Cleared 3/13/2023 RUBEN VASQUEZ

Contact Information

Architect Mizuki,, Steve Massanori; Lic. No.: NA22676       ,
Contractor M T E Construction Inc; Lic. No.: 811619-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/5/2023 Approved DAVID SCANTLIN
Deputy Drilled-In Anchors 7/27/2023 No Access for Inspection DAVID SCANTLIN
Deputy Drilled-In Anchors 8/10/2023 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 8/29/2023 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 9/27/2023 Approved DAVID SCANTLIN
PLUMBING-Rough 9/27/2023 Approved DAVID SCANTLIN
Deputy Drilled-In Anchors 10/23/2023 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 10/25/2023 Approved DAVID SCANTLIN
Deputy Drilled-In Anchors 3/14/2024 Conditional Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 4/24/2024 Not Ready for Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 4/24/2024 Approved KRISTEN CAUSEY
Green Building Rough 4/24/2024 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 5/6/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 5/21/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 5/21/2024 Approved KRISTEN CAUSEY
Green Building Rough 5/21/2024 Approved KRISTEN CAUSEY
HVAC-Rough 5/21/2024 Approved KRISTEN CAUSEY
PLUMBING-Rough 5/21/2024 Approved KRISTEN CAUSEY
Insulation 5/28/2024 Partial Approval DAVID SCANTLIN
Drywall Nailing 7/17/2024 Approved DAVID SCANTLIN
Shower Pan 10/23/2024 Approved KRISTEN CAUSEY
Final 3/28/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 3/28/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/28/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 3/28/2025 Approved DAVID SCANTLIN
Final 4/10/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 4/10/2025 Approved DAVID SCANTLIN