9750 N AMESTOY AVE 91325
Certificate Information: 9750 N AMESTOY AVE 91325
- Application / Permit
- 23014-20000-00780
- Plan Check / Job No.
- B23VN02536
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN- ADDITION AND MAJOR REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING UNIT WITH ATTACHED GARAGE TO BECOME A 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 3-CAR GARAGE AND ATTACHED 2-CAR CARPORT NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 3/24/2025
- Issuing Office
- Current Status
- Issued on 3/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | JAD BASMA |
| Corrections Issued | 3/4/2023 | JAD BASMA |
| Quality Review Completed | 3/14/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 3/31/2023 | JAD BASMA |
| Plan Check Approved | 4/17/2023 | JAD BASMA |
| Plan Check Approved | 6/20/2023 | JAD BASMA |
| Plan Check Approved | 3/24/2025 | JAD BASMA |
| Issued | 3/24/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/21/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 4/7/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 4/11/2023 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 4/15/2023 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 4/15/2023 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/13/2026 | Approved | CHRISTOPHER ROJAS |
| Sewer | 1/13/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 3/9/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/10/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 4/17/2026 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 5/7/2026 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/27/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 5/28/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Steel/Welding | 5/29/2026 | Conditional Approval | JOSE AVILA |